A construction estimate is only as good as the drawings behind it. A rough order of magnitude (ROM) comes from a few facts and a past project, a parametric estimate from a cost per square foot, and a detailed estimate from a full takeoff. Here is what each type needs, how far off it can be, and which one a bid needs.

  • ROM, parametric, assemblies and detailed estimates compared
  • AACE's five estimate classes and their accuracy ranges
  • Which estimate each design stage supports

Written by

Navtej, Chief Estimator

B.Sc. in Civil Engineering, Master's in Quantity Surveying. Runs the estimating department at E 4 Estimators.

  • 01

    Published October 28, 2026

  • 02

    9 min read

01

The short answer

Construction estimates come in types because drawings come in stages. Early on there is a site, a use and a size, and the estimate is a rough order of magnitude built from a similar past project. At schematic design there are floor plans and elevations, and the estimate is parametric: an area or a count multiplied by a historical cost per unit. At design development the systems have been chosen, and the estimate prices assemblies such as a foundation, an exterior wall or a roof. At construction documents every item can be measured, and the estimate is detailed: a quantity takeoff priced line by line.

Each step narrows the range the number can be wrong by. AACE International, the cost engineering association, sorts estimates into five classes by how mature the design is, from Class 5 at the earliest concept to Class 1 at bid. This guide walks through the types contractors meet, what each one needs, and why a bid needs the last one.

02

The five AACE estimate classes

AACE International Recommended Practice 56R-08 classifies cost estimates for building and general construction. The class is set by how mature the design deliverables are, shown roughly as a percentage of complete definition. The expected accuracy range is the typical variation of the final cost from the estimate at an 80% confidence level, after contingency has been applied. The figures below are from Table 1 of the August 2020 revision.

Class 5Design definition0% to 2%Typical useConcept screening, functional areaTypical methodSquare foot or square metre factoring, parametric models, judgment or analogyExpected accuracy rangeLow -20% to -30%; high +30% to +50%
Class 4Design definition1% to 15%Typical useSchematic design or concept studyTypical methodParametric models, assembly-driven modelsExpected accuracy rangeLow -10% to -20%; high +20% to +30%
Class 3Design definition10% to 40%Typical useDesign development, budget authorization, feasibilityTypical methodSemi-detailed unit costs with assembly-level line itemsExpected accuracy rangeLow -5% to -15%; high +10% to +20%
Class 2Design definition30% to 75%Typical useControl or bid/tender, semi-detailedTypical methodDetailed unit cost with forced detailed takeoffExpected accuracy rangeLow -5% to -10%; high +5% to +15%
Class 1Design definition65% to 100%Typical useCheck estimate or pre-bid/tender, change orderTypical methodDetailed unit cost with detailed takeoffExpected accuracy rangeLow -3% to -5%; high +3% to +10%

Two cautions come with the table, and AACE states both. The ranges assume a realistic contingency and an unbiased estimate; for a weak project team or a complex, risky project, the high side can be two to three times wider. And the class comes from the state of the deliverables, not from the percentage: a set described as half complete but with the structural or mechanical system still undecided supports a lower class than the percentage suggests.

03

Rough order of magnitude (ROM) estimates

A rough order of magnitude estimate, a ROM or order-of-magnitude estimate, is the first number on a project: the one that decides whether to keep going. It is Class 5 work. The inputs are a building type, a gross area or a count of units, a location and a rough schedule, and the method is comparison. The estimator takes a completed project of the same type, adjusts its cost for size, location, date and the differences that are known, and states the result as a range rather than a figure.

What a ROM is for: go or no-go decisions, land and financing conversations, a budget before an architect is engaged, and the first reply to a change request before the priced proposal. What it is not for: a bid, a fixed price or a subcontract. The range in the table is the honest width of the number, and a contractor who commits at that stage carries that width as risk.

How to make a ROM useful

  • Say what it is based on: the reference project, the area, the date of the costs and the adjustments made.
  • State it as a range, or as a figure with the expected range next to it.
  • List the exclusions: site work, utilities, land, design fees, permits, furniture, escalation, whichever are not in.
  • Date it. Construction costs move, and a ROM from a year ago is a different number.

04

Parametric estimating

Parametric estimating prices a project from one or a few measurable parameters and a cost per unit of that parameter taken from past projects: cost per square foot of a warehouse, per bed of a hospital, per key of a hotel, per stall of a parking structure, per linear foot of pipeline. AACE lists parametric models as the typical method for Class 5 and Class 4 estimates, which makes it the main tool at concept and schematic design. A square foot estimate is the simplest parametric estimate, with one parameter; a parametric model uses several, such as area, number of stories, perimeter and floor-to-floor height, each with its own factor.

The method has four steps. Choose the parameter that drives the cost. Find the unit cost from completed projects of the same type, your own job cost records before anyone else's. Adjust it for location, for the time between those projects and this one, and for the size of the job, since cost per unit tends to fall as buildings get bigger and rise as they get smaller. Then multiply, and add the items the parameter does not carry, such as site work, demolition and anything unusual about the site.

A parametric estimate is only as good as its reference data, and that is its limit. It assumes the new building resembles the ones behind the unit cost. A deep foundation, a long utility run, a phased renovation in an occupied building or a short schedule all sit outside the parameter and have to be added by judgment. It also says nothing about quantities: a cost per square foot does not tell you how many doors there are or how much steel. For that you need a quantity takeoff.

05

Assemblies (systems) estimates

By design development the systems have been chosen: the foundation type, the structural frame, the exterior wall, the roof, the mechanical system. An assemblies estimate prices each system as a unit, measured in its own quantity: square feet of exterior wall, square feet of roof, square feet of slab on grade, tons of cooling. It is the Class 3 method in the table, semi-detailed unit costs with assembly-level line items, and the usual basis of a design development budget check.

Assemblies estimates are usually organized by building element, in UniFormat, rather than by trade, in MasterFormat, because the decisions at this stage are about elements. The two systems are compared in our CSI MasterFormat guide. A design development set is also where a quantity takeoff starts to pay: the plans, sections and schedules are complete enough to measure most of the structure and envelope, with the finishes and MEP still carried by assembly.

06

Detailed (unit price) estimates

A detailed estimate is built from a quantity takeoff: every item on the drawings measured in its own unit, then priced with material, labor and equipment on each line, organized by MasterFormat division, with profit, contingency and sales tax shown separately. It is Class 2 and Class 1 work, and it is the only type a fixed-price bid should be built on, because it is the only type whose quantities can be checked against the drawings line by line.

It needs construction documents, or close to them. On a set that is still at design development a detailed estimate can still be made, but the lines measured from incomplete drawings are labelled as assumed, so the reader knows which numbers will move. That is how our cost estimates are built. The sample estimates show the layout, with quantities, units and the trade sections, and the general conditions guide covers the project costs that sit above the trade lines.

Detailed estimates take longer because measuring takes longer. A typical set is returned in 1–2 business days; larger or more complex sets take 7–15 days. A parametric number takes an afternoon, which is the trade: speed early, precision when the drawings allow it.

07

Which estimate at which stage

Pre-design or conceptWhat existsSite, use, gross area, rough scheduleEstimate typeRough order of magnitudeAACE classClass 5
Schematic designWhat existsFloor plans, elevations, outline specificationEstimate typeParametric: cost per square foot or per unitAACE classClass 5 to 4
Design developmentWhat existsSystems chosen; sections, schedules, draft specificationsEstimate typeAssemblies, with a takeoff of structure and envelopeAACE classClass 3
Construction documentsWhat existsFull drawings and specificationsEstimate typeDetailed unit price estimate from a full takeoffAACE classClass 2 to 1
Change ordersWhat existsSketch or bulletin drawingsEstimate typeROM first, then a detailed priceAACE classClass 1

A bid is the one place the type is not optional. The owner's design stage decides what can be measured, but the contractor's price is fixed either way, so a bid built from a parametric number carries the Class 5 range as risk. The usual fix on an incomplete set is to measure what can be measured, carry allowances for what cannot, and say so in the proposal.

08

Mistakes that cost money

  • Bidding from a square foot number. A parametric estimate tells you whether to pursue a job, not what to bid.
  • Comparing estimates of different classes. A Class 5 budget and a Class 2 bid that differ by a quarter are not in conflict; the budget was never that precise.
  • Reading the accuracy range as a promise. The AACE ranges assume contingency has been carried and the project is run well; weak definition and risky conditions widen them.
  • Applying a national cost per square foot without adjusting for the city, the year and the size of the building.
  • Carrying an item twice: once inside a unit cost that already includes it, and again as a separate line. Know what the reference cost includes.
  • Leaving out the exclusions list. A number without its exclusions gets quoted without them too.

09

What we produce

We produce detailed estimates and the quantity takeoffs behind them, measured from the drawings you send, for general contractors and subcontractors across the trades and for mechanical, electrical and plumbing scopes. Early-stage sets are estimated too, with the assumptions labelled on their lines. The fee is $180–$250 per estimator per day, by project complexity; see how our fees work.

About the author

Navtej, Chief Estimator

B.Sc. in Civil Engineering, Master's in Quantity Surveying. Runs the estimating department, sets the standards every estimate is checked against and reviews high-stakes bids.

Meet the team

Questions contractors ask

What is a ROM estimate in construction?

A rough order of magnitude estimate: the earliest cost figure, made from a building type, a size and a comparable past project before drawings exist. AACE classes it as Class 5, with an expected accuracy range of -20% to -30% on the low side and +30% to +50% on the high side.

What is parametric estimating?

Pricing a project from a measurable parameter, such as gross square feet or number of beds, multiplied by a cost per unit taken from completed projects and adjusted for location, time and size. It is the main method at concept and schematic design.

What is a Class 5 estimate?

The least defined class in the AACE system, made when 0% to 2% of the project definition exists. It is used to screen a concept, usually by square foot factoring, parametric models or comparison with a past project.

How accurate is a detailed estimate?

AACE gives Class 1 estimates, built from a detailed takeoff of complete drawings, an expected range of -3% to -5% low and +3% to +10% high at 80% confidence, after contingency. The range depends on the drawings being complete and the pricing being current.

What is the difference between a budget estimate and a bid estimate?

A budget estimate is the owner's or designer's planning number at an early stage, usually parametric or assemblies based. A bid estimate is the contractor's priced takeoff of the final drawings, and it becomes a contract price. They are different classes and should not be expected to match.

Can you estimate from schematic drawings?

Yes. We measure what the set shows and label the rest as assumed, so you can see which lines will move when the drawings do.

Keep reading

Where this guide leads.

The services and sample estimates behind this guide, and the guides that pair with it.