Guide · Estimating basics

General conditions in construction: what they are, and how to estimate them.

General conditions are the cost of running a project that no trade carries: supervision, the site office, temporary power and water, cleanup, safety and closeout. They are priced from the schedule, not as a percentage. Here is what the term means, what the list usually includes and how to estimate it.

  • General conditions, general requirements and overhead compared
  • A checklist of the items contractors carry
  • Why they are priced by the month, not by percentage

Written by

Navtej, Chief Estimator

B.Sc. in Civil Engineering, Master's in Quantity Surveying. Runs the estimating department at E 4 Estimators.

  • 01

    Published October 27, 2026

  • 02

    Updated November 10, 2026

  • 03

    7 min read

01

The short answer

General conditions are the project-specific costs of running a construction job that are not part of any trade's work: the superintendent and project manager, the site office, temporary power, water and toilets, fencing, dumpsters, cleanup, safety, surveying and layout, and closeout. Every project has them, and they grow with the schedule rather than with the quantity of work.

The term has a second meaning. The General Conditions of the Contract is the document that sets the rules between owner and contractor: payment, changes, time, insurance, claims and termination. AIA Document A201 and ConsensusDocs 200 are the common forms. Contractors say "general conditions" for both, and the cost meaning is the one an estimate carries. This guide is about the cost.

02

General conditions, general requirements and overhead

Three terms get mixed up on bid day. They describe different things, and an estimate that keeps them apart is easier to check and easier to defend.

General requirementsWhat it isDivision 01 of the specification: the owner's rules for how the work is run. Summary of work, payment procedures, submittals, quality requirements, temporary facilities and controls, execution and closeout.Where it shows upThe project manual. It tells you what to carry; it does not price anything.
General conditionsWhat it isThe contractor's cost of meeting Division 01 and running the site: staff, temporary facilities, utilities, cleanup, safety, closeout.Where it shows upIts own section of the estimate, usually at the top of the bid summary, built from the schedule.
OverheadWhat it isThe cost of running the company rather than the project: the main office, estimating, accounting, officers, marketing, vehicles not assigned to a job.Where it shows upA markup on the whole estimate, often paired with profit as "overhead and profit".

The line between general conditions and overhead is whether the cost would disappear if the project did. A superintendent assigned to the job is general conditions. The payroll clerk who processes the superintendent's timesheet is overhead. Some contractors call the first group "job overhead" and the second "home office overhead", which says the same thing.

Division 01 is one of the 50 divisions in CSI MasterFormat. Its sections are where most general conditions items are born: 01 33 00 Submittal Procedures, 01 40 00 Quality Requirements, 01 50 00 Temporary Facilities and Controls and 01 70 00 Execution and Closeout Requirements are the ones to read line by line before pricing.

03

What goes into general conditions

The list changes with the project, the contract and the owner. These are the items that come up on most commercial jobs, grouped the way a general conditions sheet is usually laid out.

Project staff

  • Superintendent, and assistant superintendents on larger or phased work
  • Project manager and project engineer, full time or a share of their time
  • Safety manager where the specification or the contractor's own program requires one
  • Field clerk or office manager, where the site office is staffed
  • Surveyor or layout crew, when layout is not carried by the trades

Temporary facilities

  • Site office and storage trailers, including delivery, setup and removal
  • Temporary toilets, hand-wash stations and drinking water
  • Perimeter fencing, gates, barricades and covered walkways
  • Project signage, and the owner's sign where the specification calls for one
  • Temporary roads, parking, laydown areas and crane pads
  • Temporary stairs, ladders, guardrails and protection of finished work

Temporary utilities and services

  • Temporary power: service connection, distribution, lighting and monthly usage
  • Temporary water and the meter
  • Temporary heat, cooling and dehumidification, especially for finishes in winter
  • Phone, internet and the project management or document control platform

Site operations

  • Daily and final cleanup, including laborers, dumpsters and hauling
  • Dust, noise, erosion and stormwater controls, and street cleaning
  • Material handling: forklift, hoist or crane where it is not in a trade's scope
  • Small tools, consumables and fuel for equipment on site
  • Pickup trucks, fuel and travel; lodging and per diem on out-of-town work

Administration and closeout

  • Permits and inspection fees, when the contract leaves them with the contractor
  • Builder's risk and general liability insurance, and bond premiums, when the bid form does not list them separately
  • Testing and inspection paid by the contractor, where the specification assigns it
  • As-built drawings, operation and maintenance manuals, training and warranties
  • Punch list labor and final cleaning

Insurance, bonds and permits are sometimes listed on the bid form as their own lines. When they are, keep them out of general conditions so they are not carried twice.

04

How general conditions are estimated

General conditions are driven by time. A superintendent costs the same per week whether the building is finishes-heavy or structure-heavy, and the site office is rented by the month, not by the square foot. So the estimate starts with the schedule.

  • Set the duration. Build a summary schedule from notice to proceed to substantial completion, then to final completion, and decide which staff and facilities are needed in each phase.
  • List the time-based items. For each staff position and each rented facility, the quantity is weeks or months, the rate is the loaded weekly or monthly cost, and the line is the two multiplied.
  • Add the one-time items. Mobilization, fence installation, trailer delivery and removal, the project sign, final cleaning and closeout documents are priced once, not by the month.
  • Add the quantity-based items. Dumpsters by the pull, temporary power by the month plus usage, protection by the area protected.
  • Read Division 01 against the list. Add anything the specification requires that the standard list does not carry: a full-time safety officer, a webcam, a specific scheduling software, weekly owner meetings with minutes, a commissioning agent.
  • Check the total against the duration. If the schedule slips a month, the general conditions line should tell you what a month costs. That number is also the basis of a delay claim later, so it needs to be real. If general conditions get their own line on the schedule of values, it is also the figure you bill against each month.

Many contractors instead carry general conditions as a percentage of the trade cost. The habit comes from budgets, where there is no schedule yet. In a bid it is the most common way to get general conditions wrong, because a slow, phased renovation and a fast new build can have the same trade cost and very different durations. A percentage can be a check on the built-up number; it should not replace it.

05

Mistakes that cost bids

  • Pricing the duration in the bid documents rather than the duration the work will take. If the contract period is short and liquidated damages apply, the estimate should show the acceleration cost or the risk.
  • Carrying cleanup twice: once in general conditions and once in each subcontractor's quote. Decide who cleans up after whom, and say so in the scope letters.
  • Missing items that live only in Division 01, such as a dedicated safety manager, a specific project management platform, or owner-furnished items the contractor must receive, store and install.
  • Forgetting phased or occupied work: temporary partitions, after-hours work, security escorts and repeated moves of the site facilities.
  • Pricing winter work without temporary heat and enclosure, or summer concrete without the cost of controlling it.
  • Leaving project staff in overhead because they are salaried. If they are assigned to the job, the job carries them.

06

Where general conditions sit in our estimates

Our cost estimates price the trade work by CSI division, with material, labor and equipment on each line and profit, contingency and sales tax shown separately. Labor is built from journeyman, supervisor and unskilled rates, so crew-level supervision is in the trade lines. The project-level staff and site costs described here depend on your own schedule, staff and site, so they belong in a general conditions section you build from the checklist above and put at the top of the bid summary.

The sample estimates show how the trade sections are laid out and where the summary sits. For the quantities behind them, see quantity takeoffs and the trades we estimate.

About the author

Navtej, Chief Estimator

B.Sc. in Civil Engineering, Master's in Quantity Surveying. Runs the estimating department, sets the standards every estimate is checked against and reviews high-stakes bids.

Meet the team

Questions contractors ask

Are general conditions the same as overhead?

No. General conditions are the costs of running one project: supervision, temporary facilities, utilities, cleanup and closeout. Overhead is the cost of running the company, spread across all projects as a markup.

What is the difference between general conditions and general requirements?

General requirements are Division 01 of the specification, the owner's rules for running the work. General conditions are what it costs the contractor to follow those rules and run the site.

What percentage of a project is general conditions?

There is no reliable percentage, because general conditions follow the schedule rather than the trade cost. Build them from the duration and the Division 01 requirements, then use a percentage only as a check.

Does a subcontractor have general conditions?

Yes, on a smaller scale: a foreman's non-productive time, a storage container, lifts, cleanup of its own work and its share of temporary facilities. Subcontractors often carry them inside their labor rates, which is why scope letters should say what is included.

What are extended general conditions?

The added time-based costs when a project runs longer than planned for reasons the contractor did not cause. They are calculated from the same weekly or monthly rates as the original estimate, which is one reason to build that estimate from real rates.

Keep reading

Where this guide leads.

The services and sample estimates behind this guide, and the guides that pair with it.

Next bid

Bid due soon? Send the drawings.

Send the drawings, the scope and the bid date. We reply with a quote within 30 minutes during business hours.