What is a schedule of values in construction?

A schedule of values breaks the contract sum into lines, each with a dollar value, and every progress payment is measured against it. Here is where the contract requires it, how the AIA G702 and G703 pay application uses it, how to build one from the estimate, and the mistakes that hold up payment.

  • What it is, and where A201 and Division 01 require it
  • The G702 and G703 pay application, column by column
  • Building one from the estimate, and what gets it sent back

Written by

Navtej, Chief Estimator

B.Sc. in Civil Engineering, Master's in Quantity Surveying. Runs the estimating department at E 4 Estimators.

  • 01

    Published November 2, 2026

  • 02

    Updated November 9, 2026

  • 03

    8 min read

01

The short answer

A schedule of values is the contract sum broken into lines, one for each part of the work, with a dollar value on each line and a total that equals the contract sum exactly. The contractor prepares it after award and before the first pay application. From then on, every progress payment is measured against it: each month the contractor reports how much of each line is complete, and is paid that share, less retainage.

It looks like an estimate summary, but it does a different job. The estimate is how the contractor built the price, and it stays with the contractor. The schedule of values is how the agreed price is billed, and the owner and the architect read it every month.

02

Where the contract asks for it

AIA Document A201-2017, the general conditions used on many US building contracts, requires it in Section 9.2. Where the contract is a stipulated sum or a guaranteed maximum price, the contractor submits a schedule of values to the architect before the first application for payment, allocating the entire contract sum to the various portions of the work. It is prepared in the form, and with the supporting data, the architect requires. Unless the architect objects, it becomes the basis for reviewing every application for payment, and later changes to it go through the same review.

Section 9.3.1 then ties billing to it. At least ten days before each progress payment date, the contractor submits an itemized application for payment prepared in accordance with the schedule of values, with the backup the owner or architect requires. Under Section 9.4.1 the architect has seven days to certify the full amount, certify part of it and give the reasons, or withhold certification.

The project specification usually adds the detail. In CSI MasterFormat it is Section 01 29 73, Schedule of Values, in Division 01 under 01 29 00, Payment Procedures. That section can set the form, how far the breakdown has to go, and limits on lines such as bonds, insurance and mobilization. Read it before building the schedule, not after the schedule comes back.

Other contracts work the same way with different forms. Contracts written on EJCDC documents use its C-620 application for payment. On federal fixed-price construction contracts, FAR 52.232-5 requires each progress payment request to itemize the amounts requested against the elements of work in the contract.

03

The G702 and G703 pay application

On AIA contracts the pay application is two forms. G702, Application and Certificate for Payment, is the summary page the contractor signs and the architect certifies. G703, the continuation sheet, is the schedule of values with each period's progress filled in: one row per line, in these columns.

A. Item no.What goes in itThe line number, kept the same on every application
B. Description of workWhat goes in itThe line as it reads on the accepted schedule of values
C. Scheduled valueWhat goes in itThe value of the line on the schedule of values
D. Work completed, from previous applicationWhat goes in itThe total of columns D and E on the last application
E. Work completed, this periodWhat goes in itWork installed since the last application, including stored materials that have now been installed
F. Materials presently storedWhat goes in itMaterials delivered and stored but not yet installed, and not counted in D or E
G. Total completed and stored to dateWhat goes in itD + E + F. The percentage column beside it is G ÷ C
H. Balance to finishWhat goes in itC − G
I. RetainageWhat goes in itUsed where the retainage rate varies from line to line

The G702 carries the totals: the original contract sum and the net change by change orders, the total completed and stored (column G), retainage, previous certificates for payment, and the current payment due. A change order summary on the same page lists the approved additions and deductions.

Subcontractors bill the general contractor the same way, and AIA publishes subcontractor versions, G702S and G703S, with the same columns. When a subcontractor's lines match the general contractor's, its application rolls up into the general contractor's without being re-sorted.

04

How to build one from the estimate

Start from the estimate the price came from, not from a blank sheet. The bid summary by CSI division gives the first cut of lines, and the detailed estimate gives the quantities and the split between material and labor that make each line measurable. Then:

  • Read Section 01 29 73 and the owner's form first: the breakdown required, any lines that must appear, and any limits on mobilization, bonds and insurance.
  • Match the lines to how the work is bought out: one line per subcontract or per specification section.
  • Split by building, floor or area where the work is phased.
  • Split material from labor, or furnish from install, on high-value and long-lead items such as switchgear, air handling units, curtain wall and structural steel, so stored materials can be billed in column F before they are installed.
  • Give general conditions, bonds and insurance their own lines where the specification allows. General conditions follow the schedule, so they are easiest to bill by the month.
  • Decide where overhead and profit go. Some contracts require them spread across the lines; EJCDC C-700, for example, requires each item to include an appropriate amount of overhead and profit. Others allow a separate line. Follow the specification.
  • Add lines for allowances, accepted alternates and, where the specification lists them, closeout items such as operation and maintenance manuals, training and record documents.
  • Make the lines add up to the contract sum to the cent, and keep the estimate as the backup. Section 9.2 lets the architect ask for data that supports the values.

The quantities behind the estimate also make progress easy to measure later. A line measured in linear feet of conduit, square feet of drywall or tons of steel can be billed on the share installed, and anyone can check it on site. A line called Electrical, with no quantity behind it, is billed on opinion, and opinions get argued every month.

05

Front-loading, and why reviewers push back

Front-loading, or front-end loading, means putting more value into the early lines, such as mobilization, sitework and foundations, than that work is worth, so the contractor is paid ahead of the work. It helps cash flow for a few months. Owners, architects and sureties look for it, because payment is meant to follow the work actually performed, and the architect can object to a schedule that is plainly loaded.

It also costs the contractor later. The later lines may not cover the work left in them, and when scope is deleted, the scheduled value can be the starting point for the credit. Back-loading, the opposite habit, finances the owner's project with the contractor's money. Valuing each line at its cost plus its share of the markup avoids both.

06

Billing against it each month

  • Measure each line's progress from the work in place, not from the money spent. Where the line has a quantity, bill the share installed.
  • Bill stored materials with their backup. Under A201-2017 Section 9.3.2, materials suitably stored on site are paid for unless the contract says otherwise, and off-site storage needs the owner's approval in advance, with procedures that establish the owner's title. Once installed, the material moves from column F to column E.
  • Add change orders as new lines. Keep the original scheduled values as they were and list each approved change order below them, so the G702's net change by change orders and the G703 agree. Under Section 9.3.1.1, work authorized by a construction change directive but not yet in a change order can be billed too.
  • Show retainage the way the contract sets it: a rate on completed work and one on stored material on the G702, or line by line in column I where the rates vary. The rate comes from the contract, and on public work sometimes from state law.
  • Bill what is in place, not what will be in place by the payment date. An application that runs ahead of the work gets cut, and under Section 9.5.1 the architect can withhold certification in whole or in part, as far as needed to protect the owner.
  • Keep subcontractors on the same billing cycle and lines, with the lien waivers the contract asks for.

07

Mistakes that hold up payment

  • Lines too broad to measure, so every application turns into an argument about percent complete.
  • Ignoring the limits in Section 01 29 73 on mobilization, bonds and insurance, so the schedule comes back before the first payment.
  • No split between material and labor on long-lead equipment, so stored materials cannot be billed until they are installed.
  • Changing the original scheduled values to absorb a change order instead of adding a line, so nobody can trace the contract sum.

08

A checklist before you submit it

  • Built from the estimate behind the contract price, with that estimate kept as backup
  • In the form, and to the breakdown, that Section 01 29 73 and the owner require
  • Lines matched to subcontracts or specification sections, and split by area where the work is phased
  • Material split from labor on items that will be stored before they are installed
  • General conditions, bonds, insurance, allowances and alternates on their own lines where allowed
  • Overhead and profit placed the way the contract requires
  • Values that follow cost, with no front-loading
  • A total equal to the contract sum, to the cent

09

Where we fit

A schedule of values is only as good as the estimate under it. Our cost estimates come with a bid summary priced by CSI division and a detailed estimate with the quantity, unit, material and labor on every line, in Excel and PDF. That is the breakdown a schedule of values is built from, and the quantity takeoff behind it gives each line a quantity to bill progress against. The sample estimates show the layout.

When the scope changes after award, we price the change order from the revised drawings, so the new line on the schedule has the same kind of backup as the original ones. The fee is $180–$250 per estimator per day, by project complexity; see how our fees work. Send the drawings for a quote.

About the author

Navtej, Chief Estimator

B.Sc. in Civil Engineering, Master's in Quantity Surveying. Runs the estimating department, sets the standards every estimate is checked against and reviews high-stakes bids.

Meet the team

Questions contractors ask

What is a schedule of values in construction?

A list of the parts of the work with a dollar value for each, adding up to the contract sum. The contractor submits it before the first pay application, and each progress payment is worked out from the share of each line that is complete, less retainage.

What is the difference between the AIA G702 and G703?

G702 is the summary page of the pay application: the contract sum, change orders, work completed, retainage and the payment due, signed by the contractor and certified by the architect. G703 is the continuation sheet: the schedule of values, line by line, with the progress on each.

What is front-loading a schedule of values?

Putting more value into early lines, such as mobilization and foundations, than that work is worth, so the contractor is paid ahead of the work. Reviewers look for it and can object to the schedule, and it leaves the later lines short.

How do change orders show on a schedule of values?

As new lines below the original ones, each with its approved value, so the original contract sum stays traceable. The G702 carries the net change by change orders and a summary of the additions and deductions.

Keep reading

Where this guide leads.

The services and sample estimates behind this guide, and the guides that pair with it.

Next bid

Bid due soon? Send the drawings.

Send the drawings, the scope and the bid date. We reply with a quote within 30 minutes during business hours.