What is retainage in construction?
Retainage, also called retention, is a percentage of each progress payment that the owner holds back until the work is substantially or finally complete. Here is where it sits on the pay application, what AIA A201 and federal contracts say about it, how Canadian holdback differs, and how to keep it from draining your cash flow.
- Where retainage sits on the G702 and G703
- When A201 and the FAR release it
- How to plan for the cash it ties up
Written by
Navtej, Chief Estimator
B.Sc. in Civil Engineering, Master's in Quantity Surveying. Runs the estimating department at E 4 Estimators.
- 01
Published November 9, 2026
- 02
9 min read
01
The short answer
Retainage is a percentage of each progress payment that the owner holds back and pays later, once the work is substantially complete or the job is closed out. The amount withheld builds up with every payment, and the contractor holds a share of it against each subcontractor in turn. Money the owner still holds is the owner's assurance that the punch list gets finished, defects get corrected and the closeout paperwork arrives.
The percentage is set in the contract, not in the general conditions. The common figures are five and ten percent: ten is the most a federal contracting officer may withhold, and five is New York's cap on larger private projects. Some contracts drop the rate once the work is half done. In Canada the equivalent amount is called holdback, and it works differently, as explained below.
02
What the contract says
AIA Document A201-2017, the general conditions used on many US building contracts, says that each Application for Payment shall reflect retainage if the contract documents provide for it (Section 9.3.1). That is all A201 says about the rate: the percentage, and any step down later in the job, are written into the owner-contractor agreement or the supplementary conditions. Read both before you bid.
Release starts at substantial completion. Under Section 9.8.5, once the owner and contractor have accepted in writing the responsibilities assigned to them in the Certificate of Substantial Completion, and the surety has consented if there is a bond, the owner pays the retainage that applies to the work, adjusted for work that is incomplete or not in accordance with the contract documents. So under A201 retainage does not wait for final payment; it is due at substantial completion, less an amount held against the punch list.
The rest comes with final payment. Section 9.10.2 says that neither final payment nor any remaining retained percentage is due until the contractor submits an affidavit that payrolls, material bills and other indebtedness connected with the work have been paid, a certificate that the insurance required after final payment is in effect, a statement that it knows of no reason the insurance will not be renewable, the surety's consent to final payment, documentation of special warranties, and, if the owner requires, releases and waivers of liens. Every item missing from that list is retainage you are not being paid.
One more clause matters on real jobs: under Section 9.9.1, if the owner occupies part of the building early, the owner and contractor agree in writing who carries payments, retainage, security, maintenance, utilities, damage and insurance for that portion.
AIA publishes a form for each consent: G707, Consent of Surety to Final Payment, and G707A, Consent of Surety to Reduction in or Partial Release of Retainage, in which the surety approves the release and agrees that it does not relieve the surety of its obligations under the bond.
03
Where retainage sits on the pay application
On AIA's G702, Application and Certificate for Payment, retainage is line 5, in two parts: a percentage of completed work, which is columns D plus E on the G703 continuation sheet, and a percentage of stored material, which is column F. Their total, or the total of column I on the G703 where the rate varies line by line, comes off the total completed and stored to date to give the total earned less retainage. The schedule of values guide walks through the G703 columns.
| G702 line | What it shows | Where the figure comes from |
|---|---|---|
| 4. Total completed and stored to date | What it showsEverything built and stored so far, at scheduled values | Where the figure comes fromColumn G on the G703 |
| 5a. Retainage on completed work | What it showsThe owner's hold on work in place | Where the figure comes fromThe contract rate times columns D + E |
| 5b. Retainage on stored material | What it showsThe owner's hold on material not yet installed | Where the figure comes fromThe rate times column F |
| 5. Total retainage | What it showsThe full amount held to date | Where the figure comes from5a + 5b, or the total of column I where rates vary by line |
| 6. Total earned less retainage | What it showsWhat you have earned the right to be paid | Where the figure comes fromLine 4 minus line 5 |
| 8. Current payment due | What it showsThis month's payment | Where the figure comes fromLine 6 minus previous certificates (line 7) |
| 9. Balance to finish, including retainage | What it showsWhat is left to bill, plus the retainage still held | Where the figure comes fromContract sum to date (line 3) minus line 6 |
Two things follow. Retainage on the pay application is a cumulative figure, so the amount withheld this period is the difference between this month's line 5 and last month's. And stored material carries retainage too, so buying ahead of installation ties up cash twice. The G702S and G703S, the contractor-subcontractor versions, carry the same lines, which is how retainage travels down the chain.
04
Federal, state and Canadian rules
Federal contracts
On federal construction, retainage is not automatic. FAR 52.232-5(e) says that if the contracting officer finds satisfactory progress was achieved in a period, payment is made in full. If not, the officer may retain up to 10 percent of the payment until satisfactory progress is achieved. At substantial completion the officer may keep the amount considered adequate to protect the Government and must release the rest, and each separately priced building or division of the contract is paid for on completion and acceptance without retention. FAR 32.103 adds that retainage is not a substitute for good contract management.
State law
Many states cap retainage on public work, some cap it on private work, and most set a deadline for releasing it. New York's General Business Law section 756-c, for example, applies to most private projects of $150,000 or more: it lets an owner retain no more than five percent of the contract sum, bars a contractor or subcontractor from retaining a higher percentage from those below it than the owner retained from it, requires release within thirty days of final approval of the work, and charges interest of one percent a month on late release. Check the statute for the project's state before you set terms with subcontractors.
Canadian holdback
Canadian contracts hold back money too, but the holdback is created by the provincial lien statute, and its job is to protect subcontractors and suppliers who might file a lien. The rate and the release period are fixed by the statute. Alberta's Prompt Payment and Construction Lien Act requires the owner to retain 10% of the value of work done and materials furnished for 60 days from the certificate of substantial performance or completion. British Columbia's Builders Lien Act sets a 10% holdback on the greater of the value of the work provided and the payments made, released 55 days after the certificate of completion unless a lien has been filed. Every payer down the chain holds it from the payer below. Our Alberta and British Columbia pages set out the payment rules we check when we price work there.
05
What retainage does to your cash flow
Retainage is not a cost line, but it behaves like one until it is released. On a ten percent contract you end each month paid ninety cents on the dollar for work you have already paid your crews, suppliers and subcontractors for, and the missing ten builds up for the length of the job. Subcontractors who finish early feel it most: a sitework or foundation subcontractor may wait for the general contractor's substantial completion, many months after its own last day on site, unless its subcontract provides for early release.
- Read the rate, the step-down and the release trigger before you bid, and carry the cost of financing the withheld amount in your overhead or general conditions.
- Add a retainage column to the job cost report: retainage receivable, held by the owner, and retainage payable, held from subcontractors. The two should move together.
- Mirror the owner's terms in your subcontracts, within the statute: the same rate, the same release trigger, and pass-through release within the time the state allows.
- Keep the schedule of values honest. Front-loading early lines to offset retainage is the first thing a reviewer looks for, and the schedule of values guide explains why it backfires.
06
Getting it released
Under A201 the first release comes with the Certificate of Substantial Completion and the last with final payment, and each has a paperwork list. Start the closeout documents when the punch list is written, not when the last item is signed off.
- Ask for the substantial completion inspection in writing, with the punch list and the value you propose the owner keeps held against it.
- Request the surety's consent, G707A for a partial release and G707 for final payment, as soon as the date is in sight.
- Collect lien waivers and releases from every subcontractor and supplier on the owner's form. One holdout stalls the whole release; under Section 9.10.2 a bond can stand in for a waiver a subcontractor refuses to give.
- Pay subcontractors their share within the time the subcontract and the statute set. Late pass-through carries interest in states like New York.
07
Mistakes that cost contractors money
- Bidding without reading the retainage clause, then finding a ten percent hold with no step-down and release at final payment only.
- Treating retainage as profit that arrives at the end. It is cash you have already spent on labor and material; plan it as a receivable.
- Letting the closeout paperwork drift, when Section 9.10.2 makes every missing document a reason not to pay the retained percentage.
- Holding a higher percentage from a subcontractor than the owner holds from you, which New York's statute forbids.
- On Canadian work, treating the holdback as a negotiable contract term. The rate and the release period are set by the provincial statute.
08
A checklist before the first pay application
- The retainage rate, and any lower rate once the work passes a stated percentage
- Whether stored material carries retainage, and at what rate
- The release trigger: substantial completion under A201 Section 9.8.5, final approval, or a statutory period
- The consent of surety the owner will ask for, and how long the surety takes
- The closeout documents in Section 9.10.2, with a named person responsible for each
- Matching retainage terms in every subcontract, within the state's cap
09
Where we fit
Retainage is deducted from the value of work completed, and that value is measured against the schedule of values, which is built from the estimate. Our construction cost estimates are organized by CSI division with quantities, units, material and labor on every line, so your schedule of values can be drawn from them line for line. We price change orders from the revised drawings, so they go onto the G702 at a figure you can defend. The estimating fee is $180–$250 per estimator per day, by project complexity; see how our fees work. The sample estimates show the level of detail.
We estimate for contractors across the United States and Canada. Send the drawings and we confirm the scope, fee and delivery date before work starts.
About the author
Navtej, Chief Estimator
B.Sc. in Civil Engineering, Master's in Quantity Surveying. Runs the estimating department, sets the standards every estimate is checked against and reviews high-stakes bids.
Questions contractors ask
What is retainage in construction?
What is a typical retainage percentage?
When is retainage released?
Is retainage the same as holdback?
Does retainage apply to subcontractors?
Keep reading
Where this guide leads.
The services and sample estimates behind this guide, and the guides that pair with it.
Next bid
Bid due soon? Send the drawings.
Send the drawings, the scope and the bid date. We reply with a quote within 30 minutes during business hours.