Guide · Contract changes
What is a change order in construction?
A change order is the signed agreement that changes the work, the contract sum or the contract time after the contract is signed. Here is how AIA A201 defines it, how it differs from a construction change directive and a minor change, what the G701 form records, how to price a change so it gets approved, and the deadlines that cost contractors money.
- What it is, and how it differs from a directive or a minor change
- The G701 form and the steps from proposal request to signature
- How to price one, and the deadlines that cost money
Written by
Navtej, Chief Estimator
B.Sc. in Civil Engineering, Master's in Quantity Surveying. Runs the estimating department at E 4 Estimators.
- 01
Published November 3, 2026
- 02
Updated November 17, 2026
- 03
9 min read
01
The short answer
A change order is a written agreement, made after the contract is signed, that changes the work and records what the change does to the contract sum and the contract time. Added work, deleted work, substitutions and revised details all go through one. Once signed, it is part of the contract, and the contractor bills it like the rest of the work.
Most start the same way: the drawings are revised, the owner asks for something new, or the site differs from what the documents showed. The contractor prices the change, the parties agree, and everyone signs. When they cannot agree in time, a construction change directive lets the work go ahead while the price is settled.
02
How the contract defines it
AIA Document A201-2017, the general conditions used on many US building contracts, gives three ways to change the work after the contract is signed (Section 7.1.1). Each is a Modification, and Section 1.1.1 makes Modifications part of the contract documents.
| Instrument | Signed by | Used when | AIA form |
|---|---|---|---|
| Change order (7.2) | Signed byOwner, contractor and architect | Used whenAll three agree on the change, the price and the time | AIA formG701 |
| Construction change directive (7.3) | Signed byOwner and architect | Used whenThe owner needs the work done before the price or time is agreed | AIA formG714 |
| Order for a minor change (7.4) | Signed byArchitect | Used whenThe change fits the intent of the documents and changes neither price nor time | AIA formG710, Architect's Supplemental Instructions |
Section 7.2.1 defines a change order as a written instrument prepared by the architect and signed by the owner, contractor and architect, stating their agreement on the change in the work, the adjustment, if any, to the contract sum, and the adjustment, if any, to the contract time. Time is part of the agreement, so check the days before you sign, not only the dollars.
On federal fixed-price construction contracts, the Changes clause, FAR 52.243-4, lets the contracting officer order changes within the general scope of the contract by written change order. On Canadian projects under CCDC 2, Part 6 of the general conditions covers the same ground: a change order when the owner and contractor agree, and a change directive (GC 6.3) when they do not and the work has to go ahead.
The project specification adds the local rules. In CSI MasterFormat they sit in Division 01, Section 01 26 00, Contract Modification Procedures, which can set the forms, the time allowed to submit a proposal, and the backup the owner expects. Read it at bid time.
03
From request to signed change order
- Something changes: a revised drawing, an owner request, an RFI answer that adds work, or a site condition the documents did not show.
- The owner, through the architect, asks for a price. AIA's G709 Proposal Request asks for an itemized proposal for changes to the contract sum and contract time within a set number of days, and states that it is not a change order or a direction to proceed.
- The contractor prices the change and sends the proposal, often called a change order request, with its backup: quantities, labor, material, equipment, subcontractor quotes, markup and any added days.
- The parties agree. The architect prepares the change order on G701 or the owner's own form, and all three sign it.
- The contractor bills it. On the next pay application it goes on the schedule of values as a new line, and the G702 adds it to the net change by change orders.
04
What the AIA G701 form records
- The project, the contract, the change order number and date, and the owner, architect and contractor
- A detailed description of the change, with exhibits attached or referenced, including adjustments agreed for executed construction change directives
- The original contract sum or guaranteed maximum price, the net change by earlier change orders, the sum before this change order, the increase or decrease this one makes, and the new sum
- The change in contract time in days, and the new date of substantial completion
It is not valid until the architect, contractor and owner have all signed it. Owners' own forms ask for the same things. Check the running total on every one: the original sum plus every earlier change order has to equal the sum before this one. If it does not, a change order has been missed or counted twice.
05
Construction change directives and minor changes
A construction change directive is a written order, prepared by the architect and signed by the owner and architect, directing a change before the price or time is agreed (Section 7.3.1). On receiving one, the contractor proceeds promptly and tells the architect whether it agrees with the proposed method of adjustment (7.3.6). Until the cost is settled, the contractor can bill the work done under it, on the architect's interim determination (7.3.9). Once the parties agree, a change order replaces all or part of the directive (7.3.10).
The price of a directive is set by one of four methods (7.3.3): an itemized lump sum with enough backup to evaluate it; unit prices; cost plus an agreed fixed or percentage fee; or, if the contractor does not respond promptly or disagrees, the architect's determination from the reasonable expenditures and savings attributable to the change, with overhead and profit as the agreement sets, or a reasonable amount (7.3.4). In those last two cases the contractor keeps an itemized accounting with supporting data.
A minor change (7.4) is a written order from the architect for a change that fits the intent of the documents and changes neither price nor time. If you believe it does change either, notify the architect and do not proceed. A contractor who does the work without that notice waives any adjustment.
06
How to price a change order so it gets approved
Price the change the way the original work was priced: from quantities. A reviewer checks a lump sum against its backup, so give them something to check.
- Measure the change from the revised drawings: what is added, what is deleted, and what is already built or bought and now has to be removed, reworked or returned.
- Price labor, material and equipment line by line, with the crew hours behind the labor.
- Add the costs the change brings with it. The costs Section 7.3.4 allows when the architect sets the price are labor with payroll taxes, fringe benefits and workers' compensation; materials, supplies and equipment, including transportation; machinery and equipment rental, excluding hand tools; bond and insurance premiums, permit fees and sales or use taxes related to the change; and supervision and field office staff attributable to it.
- Apply the markup the contract allows for changes. Section 7.3.4 looks to the agreement first, and owners often set overhead and profit percentages for changes in their supplementary conditions. Use those, not your bid markup.
- Net the additions and deductions. Under Section 7.3.8, the credit for deleted work is the actual net cost, and where a change has both, overhead and profit are figured on the net increase, if any.
- Include the time. If the change moves the completion date, put the days and the time-related costs in the same proposal.
- Carry each subcontractor's price from its own quote, checked against the drawings.
- State the assumptions, the exclusions and how long the price holds.
07
Notice deadlines that cost money
Many changes are lost before they are priced, because the notice went in late or not at all. Under A201-2017:
- Concealed or unknown conditions (3.7.4): notify the owner and architect promptly, before the conditions are disturbed, and no later than 14 days after first seeing them.
- RFI answers (3.2.4): if the architect's response to an RFI adds cost or time, the contractor submits a claim under Article 15.
- Claims (15.1.3.1): within 21 days after the event, or after you first recognize the condition, whichever is later. A claim for more money needs that notice before you proceed with the work it covers (15.1.5), except in an emergency endangering life or property.
- Minor changes (7.4): notify before doing the work, or the adjustment is waived.
On federal work, FAR 52.243-4 gives 30 days after receiving a written change order to assert the right to an adjustment. Any other order from the contracting officer that changes the work counts as a change order only if the contractor gives written notice, and costs incurred more than 20 days before that notice are not recovered, except for defective specifications. Owners also shorten these periods in their supplementary conditions, so go by the contract you signed.
08
Mistakes that cost contractors money
- Doing extra work on a verbal instruction, with no change order, directive or written notice.
- Pricing a change as one lump sum with no quantities, so the reviewer replaces it with a number of their own.
- Pricing only the added work and forgetting the removal, the rework and the material already bought.
- Signing a change order that shows the contract time unchanged when the change took longer.
- Leaving changes unpriced until closeout, when the backup is hard to find.
09
Keeping a change order log
A change order log lists every change on the job, one row each: a number, the date and source (revised drawing, RFI, owner request or site condition), a short description, the status (being priced, submitted, approved, rejected or under a directive), the amount and days proposed and approved, and the change order it became. Check it against the pay application each month: the approved total should equal the net change by change orders on the G702.
10
A checklist before you sign
- The description matches the revised drawings or the request, referenced by number and date
- Every cost is in: added work, removal and rework, material already bought, supervision, bonds, insurance, permits and taxes
- Subcontractor prices are included and marked up as the contract allows
- The time adjustment is stated in days, with the new substantial completion date
- The running total is right
- Any directive this change order replaces is named
11
Where we fit
A change order proposal is an estimate with less time to prepare it. Our cost estimates come with quantities measured in PlanSwift, material and labor priced on every line, and a marked-up PDF of the drawings showing what was measured, and our quantity takeoffs give the measured quantities on their own. The sample estimates show the layout.
When the scope changes after award, we price the change order from the revised drawings. The fee is $180–$250 per estimator per day, by project complexity; see how our fees work. Send the revised drawings for a quote.
About the author
Navtej, Chief Estimator
B.Sc. in Civil Engineering, Master's in Quantity Surveying. Runs the estimating department, sets the standards every estimate is checked against and reviews high-stakes bids.
Questions contractors ask
What is a change order in construction?
What is the difference between a change order and a construction change directive?
What is an AIA G701?
What is a change order log?
Keep reading
Where this guide leads.
The services and sample estimates behind this guide, and the guides that pair with it.