Guide · RFIs

What is an RFI in construction?

An RFI, or request for information, is a written question from the contractor to the design team about the drawings or specifications. Here is what AIA A201 and the G716 form say about RFIs, how questions at bid time become addenda, how to write an RFI that gets a usable answer, and what to do when the answer changes the price.

  • What an RFI is, at bid time and during construction
  • How to write one that gets a usable answer
  • What to do when the answer changes the price

Written by

Navtej, Chief Estimator

B.Sc. in Civil Engineering, Master's in Quantity Surveying. Runs the estimating department at E 4 Estimators.

  • 01

    Published November 4, 2026

  • 02

    8 min read

01

The short answer

An RFI, or request for information, is a written question from the contractor to the architect or engineer, asking them to clarify, correct or complete the contract documents. A good one names the drawing or specification section it is about, says what is unclear or in conflict, suggests an answer where it can, and gives the date the answer is needed. The design team answers in writing.

An answer to an RFI is not a change order. If it adds work, cost or time, that goes through a change order or a claim, with its own notice. And RFIs start before the contract does: questions sent while the job is out to bid are answered by addendum.

02

What the contract says

AIA Document A201-2017, the general conditions used on many US building contracts, puts the RFI inside the contractor's duty to review the documents. Before starting each portion of the work, the contractor studies and compares the drawings and specifications, takes field measurements of existing conditions, and promptly reports any errors, inconsistencies or omissions it finds to the architect, as a request for information in the form the architect requires (Section 3.2.2). Nonconformities with codes and regulations that it finds are reported the same way (3.2.3). The review is made as a contractor, not as a licensed design professional.

The architect reviews and responds to RFIs in writing, within any time limits agreed or otherwise with reasonable promptness, and issues supplemental drawings and specifications where the answer needs them (4.2.14). Some owners replace reasonable promptness with a fixed number of days in their supplementary conditions.

Section 3.2.4 is where the money sits. A contractor who believes an answer adds cost or time submits a claim under Article 15. A contractor who fails to report what it found pays the costs that reporting would have avoided. One who does report is not liable for the errors, inconsistencies or omissions in the documents.

On federal construction contracts, FAR 52.236-21 says the specifications govern when they differ from the drawings, and a discrepancy in the figures, the drawings or the specifications goes promptly to the contracting officer for a written determination. Any adjustment the contractor makes without one is at its own risk and expense.

The project specification sets the procedure, in Division 01 of CSI MasterFormat. The section number varies: some specifications put it in 01 31 00, Project Management and Coordination, others in a section of its own, such as 01 26 13, Requests for Interpretation. Read it for the form to use, what each RFI must include, how long the architect has to answer (often five or seven working days), and the deadline for notice when an answer changes cost or time.

03

RFIs at bid time

Most of an estimator's questions turn up during the quantity takeoff, because measuring every item is when a missing dimension, an undrawn detail or a specification section that contradicts a drawing note shows itself. Under AIA A701-2018, the instructions to bidders, a bidder who finds errors, inconsistencies or ambiguities notifies the architect and asks for clarification in writing, to be received at least seven days before bids are due (Sections 3.2.1 and 3.2.2).

Answers come only by addendum. An answer given any other way is not binding, and bidders cannot rely on it (3.2.3). Addenda are issued no later than four days before bids are due, except one that withdraws the request for bids or postpones bid day (3.4.3), and each bid acknowledges every addendum received (3.4.4). Federal sealed bids work the same way: FAR 52.214-6 asks for questions in writing, early enough for the reply to reach every bidder, says oral explanations are not binding, and sends information given to one bidder to all of them as an amendment when it matters to their bids.

  • Send questions as the takeoff finds them, not in one batch the day before the deadline.
  • Check every addendum against the takeoff. A revised sheet changes quantities, and an answer can move scope from one trade to another.
  • If a question is still open on bid day, price it on a stated assumption and list it with the bid's clarifications, so the price can be adjusted when the answer comes.
  • Never price from a phone answer. At bid time, only an addendum binds.

04

How to write an RFI that gets a usable answer

AIA's G716 Request for Information form shows what an RFI needs: who it is to and from, the project, the issue date, an RFI number, the requested reply date, a full description of the question, the specification sections, drawings and other documents researched, the sender's recommendation, and space for the reply. When the RFI concerns a site or construction condition, the sender may recommend a solution, with its cost and schedule considerations. Owners' forms and project software ask for the same things.

  • Ask one question per RFI, so an easy answer does not wait for a hard one.
  • Cite the sheet, the detail and the specification section, and attach a marked-up clip of the drawing.
  • Say what the documents show and where they conflict, so the reviewer can see you looked.
  • Propose an answer where you can, and state any cost or time it carries. Offering two options makes a quick answer easier.
  • Give a reply-by date tied to the schedule, and say what work is held up until the answer comes.
  • Number RFIs in sequence and never reuse a number.

05

What an RFI is not

Specifications often list requests the architect will return unanswered, such as requests to approve a submittal or a substitution, or questions the documents already answer. Each of those has its own route.

RFIWhat it asksWhat the documents mean, or how to resolve a gap or conflict in themChanges price or time?Not by itself
SubmittalWhat it asksReview of shop drawings, product data or samples showing how the work will meet the documentsChanges price or time?No
Substitution requestWhat it asksApproval to use a product other than the one specified. After award, A201 Section 3.4.2 allows it only with the owner's consent, after the architect's evaluation, by change order or directiveChanges price or time?It can
Change orderWhat it asksAgreement on a change in the work, the contract sum and the contract timeChanges price or time?Yes

06

When the answer changes the price

The G716 form says it plainly: the reply is not an authorization to proceed with work involving additional cost, time or both. If an answer changes the contract documents, the change goes through a change order, a construction change directive or a minor change in the work.

  • Read every answer for scope. A sketch that adds blocking, moves a duct or upsizes a beam is added work, even when the reply calls it a clarification.
  • Give notice before you build it. Under A201 Section 3.2.4 the route is a claim under Article 15, which allows 21 days from the event (15.1.3.1), and Division 01 can set a shorter deadline, counted from the day the answer arrives.
  • Price the change from the answer and its sketch the way you would price any change order: measured quantities, labor, material and equipment, and the markup the contract allows for changes.
  • Put the RFI number on the change order request, so the reviewer can trace the cost to the answer.

07

Keeping an RFI log

An RFI log lists every RFI on the job, one row each: the number, the date sent, the subject, the drawing and specification references, who it went to, the reply-by date, the date answered, the status, any cost or time effect, and the change order, directive or minor change it led to. Review it at every project meeting. Open RFIs past their reply-by date are the ones holding up the work, and answered ones with a cost effect are the ones still to be priced.

08

Mistakes that cost contractors money

  • Building to a verbal answer. Under A201 the architect answers in writing; get it that way.
  • Doing the work an answer adds before giving notice.
  • Asking a question the documents already answer, which costs a response cycle and the reviewer's patience.
  • Using an RFI to get a substitution or a submittal approved.
  • Pricing a bid on a guess with no stated assumption, then absorbing the difference when the answer comes.
  • Sending bid questions after the deadline, so the answer never arrives as an addendum.

09

A checklist before you send one

  • One question, clearly stated
  • The sheet, detail and specification section cited, with a marked-up clip attached
  • What the documents show, and where they conflict
  • A proposed answer, with any cost or time it carries
  • A reply-by date, and the work that waits on it
  • The next number in the log

10

Where we fit

Our quantity takeoffs and cost estimates are measured from the drawings you send. Where the drawings leave something open, the assumption is labelled on the line it affects instead of being buried in a total. That gives you a ready list for your bid questions, and each line can be confirmed or taken out once the addendum answers it. The sample estimates show how assumptions are labelled. The estimating fee is $180–$250 per estimator per day, by project complexity; see how our fees work.

Our shop drawings come with a list of open questions and conflicts for you to raise as RFIs, instead of us guessing, and our as-built drawings draft the RFI responses and approved changes into a clean record set. For drawing work we confirm the sheets, the fee and the delivery date before drafting starts. Send the drawings for a quote.

About the author

Navtej, Chief Estimator

B.Sc. in Civil Engineering, Master's in Quantity Surveying. Runs the estimating department, sets the standards every estimate is checked against and reviews high-stakes bids.

Meet the team

Questions contractors ask

What is an RFI in construction?

A request for information: a written question from the contractor to the architect or engineer, asking them to clarify, correct or complete the drawings or specifications. It cites the documents involved, can suggest an answer, and gives the date a reply is needed. The answer comes back in writing.

Is an RFI response a change order?

No. AIA's G716 form says the reply is not an authorization to proceed with work involving additional cost or time. If an answer changes the work, it needs a change order, a construction change directive or a minor change, and the contractor gives notice of any cost or time before doing the work.

What is the difference between an RFI and a submittal?

An RFI asks the design team what the documents mean. A submittal shows the design team how the contractor will meet them, with shop drawings, product data or samples, for review. Specifications often return unanswered any RFI that asks for a submittal to be approved.

How long does an architect have to answer an RFI?

Under AIA A201-2017, within any time limits agreed or otherwise with reasonable promptness. Many project specifications set a number in Division 01, often five or seven working days, and allow more time when the RFI is incomplete.

Can you send an RFI during bidding?

Yes. Under AIA A701-2018 a bidder's questions go to the architect in writing, to arrive at least seven days before bids are due, and the answers come only by addendum, which every bidder acknowledges in its bid.

Keep reading

Where this guide leads.

The services and sample estimates behind this guide, and the guides that pair with it.

Next bid

Bid due soon? Send the drawings.

Send the drawings, the scope and the bid date. We reply with a quote within 30 minutes during business hours.