What is a submittal in construction?
A submittal is a drawing, data sheet, sample or report the contractor sends to the architect or engineer to show what will be installed and how, before the work is built. Here are the types, how review works under the standard AIA contract, how to run a submittal log, and why submittals come back.
- Shop drawings, product data, samples and the rest
- Who reviews what, and what approval does not cover
- The submittal log, and why submittals come back
Written by
Navtej, Chief Estimator
B.Sc. in Civil Engineering, Master's in Quantity Surveying. Runs the estimating department at E 4 Estimators.
- 01
Published October 29, 2026
- 02
Updated November 4, 2026
- 03
8 min read
01
The short answer
A submittal is anything the contractor sends to the architect or engineer of record to show what will be installed and how, before the work is built: shop drawings, product data sheets, physical samples, calculations, test reports and certificates, and at the end of the job the manuals, warranties and record drawings. The specification says which submittals each section needs, the general contractor checks and sends them, and the design team reviews them against the design.
Submittals are where the design turns into specific products and fabricated pieces, and they sit on the schedule: work that needs a submittal waits until it comes back approved, and so do the orders and the fabrication behind it. This guide covers the types, how review works under the standard AIA contract, the submittal log, and what gets submittals sent back.
02
The types of submittals
AIA Document A201-2017, the general conditions used on many US building contracts, defines the three main types in Section 3.12:
| Type | What it is | Examples |
|---|---|---|
| Shop drawings | What it isDrawings, diagrams, schedules and other data prepared specially for the project by the contractor, a subcontractor, a manufacturer, a supplier or a distributor | ExamplesSteel erection and piece drawings, rebar placing drawings, duct layouts, millwork elevations |
| Product data | What it isStandard information about a material or piece of equipment: illustrations, schedules, performance charts, instructions and brochures | ExamplesManufacturer's data sheets with the model and options marked, equipment schedules, installation instructions |
| Samples | What it isPhysical examples of materials, equipment or workmanship, which set the standard the work will be judged by | ExamplesPaint, tile, stone and brick, laminate and finish chips, hardware finishes |
Specifications add others: design calculations, test and inspection reports, manufacturers' certificates, installer qualifications and the closeout documents. How all of them are prepared and sent is set out in Section 01 33 00, Submittal Procedures, in Division 01, and each trade's section lists the submittals it requires. Our CSI MasterFormat guide explains how the divisions and sections are numbered. Shop drawings, the submittals that take the most drafting, have their own guide.
03
Action, informational and closeout submittals
Many specifications also sort submittals by what the design team has to do with them:
- Action submittals need a response. The architect or engineer reviews them and returns them with a review action. Shop drawings, product data and samples are usually action submittals.
- Informational submittals are for the record and do not need a responsive action. A201-2017 lets the contract documents identify them. Test reports, certificates and qualification statements usually fall here.
- Closeout submittals come at the end: operation and maintenance manuals, warranties and bonds, and record documents. In MasterFormat they sit in Section 01 78 00, Closeout Submittals, with operation and maintenance data in 01 78 23 and project record documents in 01 78 39.
Record documents include the as-built drawings, which show what was actually built rather than what was planned. We draft as-built drawings from field redlines as well as shop drawings.
04
How a submittal moves
Under A201-2017 the sequence is set out in Sections 3.10.2, 3.12 and 4.2.7, and most project specifications follow the same order:
- After award, the contractor prepares a submittal schedule, coordinated with the construction schedule and allowing the architect reasonable time to review.
- The subcontractor, fabricator or supplier prepares the submittal from the contract documents.
- The general contractor reviews it for compliance with the contract documents, verifies field measurements and checks coordination with the other trades, then approves it and submits it. Under Section 3.12.6, submitting it is a statement that this review was done.
- Any deviation from the contract documents is pointed out in the submittal, with its difference in cost.
- The architect, with the engineers for their disciplines, reviews it against the information given and the design concept, and returns it with a review action.
- Work that needs the submittal does not start until it is approved. Ordering and fabrication follow approval.
- If it comes back for resubmittal, the corrections are made, and the resubmittal points out in writing any change other than the ones the reviewer asked for.
Review actions vary by firm and by specification. Common ones are no exceptions taken, make corrections noted, revise and resubmit, and rejected. The first two usually let the work proceed, with the noted corrections made; the last two mean the submittal has to come back.
05
What the review does and does not cover
The architect's review is narrower than many contractors assume. Section 4.2.7 limits it to checking conformance with the information given and the design concept. It is not done to check the accuracy and completeness of details such as dimensions and quantities, or the installation and performance of equipment and systems; those stay with the contractor. Under Section 3.12.8, approval also does not relieve the contractor of responsibility for errors or omissions in the submittal.
Submittals are not contract documents either (Section 3.12.4). An approved shop drawing that differs from the contract drawings does not release the contractor from what the contract requires, unless the difference was pointed out when it was submitted and then approved in writing as a minor change in the work, or authorized by a change order or construction change directive.
The exception is delegated design. When the contract documents require the contractor to provide design services or certifications for a system, the owner and architect have to specify the performance and design criteria, and a licensed design professional does the work and signs and seals the drawings and calculations. Some stairs and railings, curtain wall anchorage and cold-formed metal framing are common examples.
06
The submittal log
A submittal log, or register, lists every submittal the project needs, and it is what keeps them moving. It is built by reading the specification section by section, adding anything the drawing notes ask for, and dating each item from the construction schedule. A useful log shows, for each submittal:
- The specification section and a submittal number
- A description and the type: shop drawing, product data, sample, informational or closeout
- Who prepares it: the subcontractor, supplier or fabricator
- The date it must be submitted, worked back from the schedule: the date the material is needed on site, less the ordering or fabrication time, less the review time
- The dates it was sent, returned and resubmitted, with the review action each time
- A long-lead flag for items such as structural steel, curtain wall, elevators and major mechanical and electrical equipment
Working back from the site date is the point. A steel package that is fabricated after approval needs its shop drawings in review well before the steel is needed, and a resubmittal adds a second review to that time. Project specifications usually say how long the reviewer has. A201-2017 ties review to the approved submittal schedule, or to reasonable promptness where there is none, and under Section 3.10.2 a contractor who does not submit a schedule, or does not keep to it, cannot claim more time or money for the time review takes.
07
Why submittals come back
- Forwarded without the contractor's review: a subcontractor's package sent on unchecked, with the wrong product or missing pages.
- Product data that is not marked up: a data sheet that covers ten models, with none selected, tells the reviewer nothing.
- A deviation from the specification that is not called out, or a substitution sent as a submittal instead of through the specification's substitution procedure.
- Missing pieces the specification asks for, such as calculations, a test report or a sample.
- Shop drawings drawn from an old revision or without the latest addenda, or with dimensions left to be field verified without saying so.
- A package split so it cannot be judged: curtain wall elevations without the anchors, or equipment without its controls.
- A gap in the contract drawings filled with a guess on the submittal, instead of an RFI first.
08
Where we fit
We prepare shop drawings, the drawn part of a submittal package, for subcontractors and fabricators: structural steel, miscellaneous metals, rebar, curtain wall and storefront, fire sprinkler with hydraulic calculations, and the other trades on our shop drawings page.
You send the contract drawings, the specification section, addenda, any approved product data or field dimensions, and the submittal date. We confirm the sheets, the fee and the delivery date before drafting starts, and anything the drawings leave open comes back to you as a question to raise as an RFI. You submit the set to the architect or engineer; we revise it to the review comments and reissue it. If the project needs an engineer's stamp, tell us at the quote stage and we will confirm what can be arranged for that project.
When we have also taken off the bid, the shop drawings start from the same measured quantity takeoff, so the quantities in the submittal agree with the quantities in the price. Send the contract set for a quote.
About the author
Navtej, Chief Estimator
B.Sc. in Civil Engineering, Master's in Quantity Surveying. Runs the estimating department, sets the standards every estimate is checked against and reviews high-stakes bids.
Questions contractors ask
What is a submittal in construction?
What is the difference between a submittal and a shop drawing?
What is a submittal log?
Who approves submittals?
What does revise and resubmit mean?
How long does submittal review take?
Keep reading
Where this guide leads.
The services and sample estimates behind this guide, and the guides that pair with it.
Next bid
Bid due soon? Send the drawings.
Send the drawings, the scope and the bid date. We reply with a quote within 30 minutes during business hours.