What is a time and materials contract in construction?
Under a time and materials (T&M) contract the contractor is paid for the hours worked, at hourly rates fixed in the contract, plus the cost of the materials. Here is what the hourly rate has to carry, how materials are paid, what a ceiling or not-to-exceed price changes, how T&M shows up in change orders, and the records that get a T&M bill paid.
- What the fixed hourly rate has to carry, and how materials are paid
- What a ceiling or not-to-exceed price changes
- T&M in change orders, and the daily records that get it paid
Written by
Navtej, Chief Estimator
B.Sc. in Civil Engineering, Master's in Quantity Surveying. Runs the estimating department at E 4 Estimators.
- 01
Published November 17, 2026
- 02
8 min read
01
The short answer
A time and materials contract, usually written T&M, pays the contractor on two measures: the labor hours worked, at hourly rates agreed in the contract, and the materials used, at their cost. There is no fixed price for the job. The total depends on how many hours and how much material the work takes, so most of the risk of an overrun sits with the owner unless the contract sets a ceiling.
The clearest published definition is in the Federal Acquisition Regulation. FAR 16.601(b) describes a time-and-materials contract as one that buys work on the basis of direct labor hours at specified fixed hourly rates that include wages, overhead, general and administrative expenses and profit, plus actual cost for materials. A labor-hour contract is the same thing where the contractor supplies no materials (FAR 16.602). On private work there is no single rule: the rates, the markups and any cap are whatever the agreement or the change order says.
02
T&M, cost-plus and lump sum compared
T&M is often confused with a cost-plus contract. Both pay for what the work actually takes, but they handle overhead and profit differently, and that changes what the estimator has to price.
| Contract | How labor is paid | Where overhead and profit sit | Who carries an overrun |
|---|---|---|---|
| Time and materials | How labor is paidHours worked, at fixed hourly rates | Where overhead and profit sitInside the hourly rates | Who carries an overrunThe owner, up to any ceiling price |
| Cost plus a fee | How labor is paidActual wages and labor burden, as the contract defines cost | Where overhead and profit sitIn a separate fee | Who carries an overrunThe owner, up to any guaranteed maximum price |
| Lump sum (stipulated sum) | How labor is paidNot paid separately; it is part of one fixed price | Where overhead and profit sitInside the fixed price | Who carries an overrunThe contractor |
The line between the first two can blur. AIA A102-2017, a cost-plus form, allows agreed rates for labor costs in place of actual costs, and says those rates stay unchanged for the duration of the agreement unless the parties sign a modification (Section 7.2.5).
T&M is the exception for whole projects. On federal work the rule is that firm-fixed-price contracts are generally used to acquire construction, priced as a lump sum, by unit prices or both (FAR 36.207). T&M turns up where the scope cannot be drawn or counted before the work starts: investigation and repair, small service work, emergency work, and changes during a job.
03
What the hourly rate has to carry
This is where T&M work is won or lost. The rate is fixed, the hours are not, and anything the rate leaves out is not paid for anywhere else. The federal payment clause, FAR 52.232-7, says the hourly rates include wages, indirect costs, general and administrative expense and profit. Before you quote a rate, check that it carries:
- The wage for the labor category, at the scale that applies to the job
- Payroll taxes, workers' compensation insurance and fringe benefits
- Field costs you will not bill as a separate line, such as small tools and supervision
- Home-office overhead
- Profit
Three details in the federal clause are worth copying into any T&M agreement, because each one settles a common argument:
- A rate for each labor category. The contract sets separate fixed hourly rates by category (FAR 16.601(c)(2)), and hours worked by someone who does not meet the category's qualifications are not paid unless the contracting officer authorizes it.
- Overtime. Unless the schedule says otherwise, the rates are not varied because work was done on overtime. With no overtime rates in the schedule, overtime has to be approved in advance and its rates negotiated.
- Part hours. Fractional parts of an hour are payable on a prorated basis.
04
How materials are paid
Materials are paid at actual cost, backed by invoices. What else can ride on them depends on the contract. Under FAR 52.232-7:
- Materials include direct materials, subcontracts for supplies and incidental services that have no labor category, other direct costs and applicable indirect costs.
- Indirect costs may be added to materials only when they are clearly excluded from the hourly rate. The same cost cannot be recovered twice.
- The contractor takes the cash and trade discounts, rebates and credits available and gives the Government credit for them.
- With narrow exceptions, the Government does not pay the prime contractor profit or fee on materials.
Private T&M agreements often allow a markup on materials, subcontractors and rented equipment. Read for it, and for what it applies to. If the agreement is silent on a markup, do not assume one.
05
Ceiling and not-to-exceed prices
A T&M contract with a cap is usually called T&M not to exceed. On federal work the cap is not optional: a time-and-materials contract may be used only if it includes a ceiling price that the contractor exceeds at its own risk (FAR 16.601(d)). The FAR is frank about why. A time-and-materials contract gives the contractor no positive profit incentive for cost control or labor efficiency, so it may be used only when the extent or duration of the work cannot be estimated accurately when the contract is placed (FAR 16.601(c)).
The ceiling comes with a duty to warn. Under FAR 52.232-7(d), if the contractor has reason to believe that the payments accruing in the next 30 days, added to everything accrued so far, will exceed 85 percent of the ceiling price, it notifies the contracting officer with a revised estimate and the reasons. The Government is not obligated to pay above the ceiling, and the contractor is not obligated to continue past it, until the contracting officer raises it in writing (52.232-7(e)).
So a ceiling is an estimate with consequences, even though the contract is not fixed price. It needs a scope, quantities and crew hours behind it, and a way to track hours against it week by week.
06
T&M in change orders
Most contractors meet T&M inside a lump sum job, when a change has to start before its price is agreed. AIA A201-2017 does not use the term, but it describes the method. A construction change directive may adjust the contract sum by cost determined in a manner the parties agree, plus a mutually acceptable fixed or percentage fee (Section 7.3.3.3). If the contractor does not respond or disagrees, the architect determines the adjustment from the reasonable expenditures and savings attributable to the change (Section 7.3.4).
In both cases the contractor keeps and presents an itemized accounting with supporting data. The costs Section 7.3.4 allows, unless the contract says otherwise, are labor with payroll taxes, fringe benefits and workers' compensation; materials, supplies and equipment, including transportation; rental of machinery and equipment, excluding hand tools; bond and insurance premiums, permit fees and sales or use taxes related to the change; and supervision and field office personnel directly attributable to it. Overhead and profit follow the agreement.
Once the cost is settled it is recorded in a change order. Where the scope of the change can be drawn, a priced lump sum agreed up front is usually quicker to get paid than tickets argued over afterward.
07
The records that get T&M paid
A T&M bill is only as good as its backup. FAR 52.232-7 has vouchers substantiated by evidence of actual payment and by individual daily job timekeeping records, allows an audit of the vouchers and supporting documents at any time before final payment, and lets the contracting officer withhold 5 percent of the labor amounts due, up to $50,000 in total, until the contractor delivers its release. Private owners ask for much the same. A daily T&M ticket should show:
- The date, the location and a description of the work done
- Each worker's name, labor category and hours, with overtime shown separately
- Materials used, with quantities, and the invoices to follow
- Equipment used, with hours
- The signature of the owner's or general contractor's representative, collected that day
08
What it means for the estimate
- Build each hourly rate from the bottom up: wage, burden, the field costs it must carry, overhead and profit. A rate copied from the last job carries that job's wage scale and insurance costs.
- Estimate the job anyway. Owners ask what T&M work is likely to cost, and a ceiling needs a number. A quantity takeoff and crew hours give you an expected total to manage against.
- Track hours and material against that estimate every week, and tell the owner early when the work is running over.
- When a T&M change becomes drawable, price it. Revised drawings turn an open-ended ticket into a cost estimate the owner can approve.
09
Mistakes that cost money
- Quoting a bare wage as the rate. Burden, overhead and profit then come out of your pocket for every hour worked.
- Starting T&M work on a verbal instruction. Get the direction, the rates and any cap in writing first.
- Tickets written up at the end of the week from memory, or never signed.
- Billing a cost as a separate line when the rate already includes it.
- No overtime rate in the agreement, and no approval before the overtime is worked.
- Running past a not-to-exceed amount without notice. The hours above it may not be paid.
10
A checklist before you start
- Hourly rates by labor category, with what each rate includes written down
- Overtime rates, and who approves overtime
- How materials, subcontractors and equipment are billed, and any markup
- The ceiling or not-to-exceed amount, and the notice required before reaching it
- The ticket form, who signs it and how often it is billed
11
Where we fit
We do not draft contracts or advise on them; a construction attorney does that. Our part is the numbers behind a T&M job: the expected quantities and labor hours, and the price of a change once it is drawn. Our construction cost estimates are built from a quantity takeoff and organized by CSI division with quantities, units, material and labor on every line, and we price change orders from revised drawings. The estimating fee is $180–$250 per estimator per day, by project complexity; see how our fees work. The sample estimates show the level of detail.
We estimate for general contractors and subcontractors across the United States and Canada. Send the drawings and we confirm the scope, fee and delivery date before work starts.
About the author
Navtej, Chief Estimator
B.Sc. in Civil Engineering, Master's in Quantity Surveying. Runs the estimating department, sets the standards every estimate is checked against and reviews high-stakes bids.
Questions contractors ask
What is a time and materials contract?
What does T&M mean in construction?
What is the difference between time and materials and cost-plus?
What is the difference between time and materials and a lump sum contract?
What is a not-to-exceed price on a T&M contract?
Keep reading
Where this guide leads.
The services and sample estimates behind this guide, and the guides that pair with it.
Next bid
Bid due soon? Send the drawings.
Send the drawings, the scope and the bid date. We reply with a quote within 30 minutes during business hours.