Guide · Contracts

What is a cost-plus contract in construction?

Under a cost-plus contract the owner pays the contractor the actual cost of the work plus a fee, instead of one fixed price. Here is how the fee is set, which costs are reimbursed and which are not, what a guaranteed maximum price changes, and why the estimate matters as much as it does on a lump-sum bid.

  • How the fee and the cost of the work are defined in AIA A102 and A103
  • What a guaranteed maximum price (GMP) adds, and what a control estimate is
  • The costs that are not reimbursed and have to be covered by the fee

Written by

Navtej, Chief Estimator

B.Sc. in Civil Engineering, Master's in Quantity Surveying. Runs the estimating department at E 4 Estimators.

  • 01

    Published November 16, 2026

  • 02

    Updated November 17, 2026

  • 03

    10 min read

01

The short answer

A cost-plus contract has two parts: the cost of the work, which the owner reimburses, and the contractor's fee, which covers home-office overhead and profit. The contractor is paid what the job actually costs, within the contract's definition of cost, plus the fee. Under a stipulated sum (lump sum) contract, by contrast, the contractor is paid one fixed price whatever the work costs.

The standard US forms come as a pair. AIA Document A102-2017 is the owner-contractor agreement where the basis of payment is the cost of the work plus a fee with a guaranteed maximum price. AIA Document A103-2017 is the same arrangement without a guaranteed maximum price. Both adopt the A201-2017 general conditions, and in both Section 5.1 defines the contract sum as the cost of the work plus the contractor's fee. AIA A133-2019 is the matching form for a construction manager as constructor.

02

How the fee is set

Section 5.1.1 of A102 and A103 leaves the fee to the parties: a lump sum, a percentage of the cost of the work, or another provision. The choice decides what happens to the fee when the cost moves.

Cost plus a percentage feeWhat the contractor is paidThe cost of the work plus a stated percentage of itWho carries a cost overrunThe owner; the fee rises with the cost
Cost plus a fixed feeWhat the contractor is paidThe cost of the work plus a lump-sum feeWho carries a cost overrunThe owner; the fee stays the same unless the work changes
Cost plus a fee with a guaranteed maximum priceWhat the contractor is paidThe cost of the work plus the fee, up to the guaranteed maximumWho carries a cost overrunThe owner up to the maximum, the contractor above it

Two details are easy to miss. Section 5.1.2 asks for the method of adjusting the fee for changes in the work; if it is left blank, Section 6.4 has the fee equitably adjusted on the same basis used to set it for the original work. And a fixed fee is not paid up front: each progress payment carries the share of the fee that the cost billed so far bears to a reasonable estimate of the probable cost of the work at completion.

On federal work, where the FAR calls these cost-reimbursement contracts (FAR 16.301-1), the percentage fee is not available. FAR 16.102(c) prohibits the cost-plus-a-percentage-of-cost system of contracting. The FAR's cost-plus-fixed-fee contract pays a negotiated fee fixed at the start, which does not vary with actual cost but may be adjusted for changes in the work (FAR 16.306).

03

What counts as cost

This is the part of the contract an estimator should read first. In A102 and A103 the cost of the work means costs necessarily incurred in the proper performance of the work, and it includes only the items set out in Article 7 (Section 7.1.1). Rates may not be higher than the standard paid at the place of the project without the owner's approval (Section 7.1.3). The reimbursable items include:

  • Wages of construction workers the contractor employs directly at the site, with the taxes, insurance and benefits based on those wages (Sections 7.2.1 and 7.2.4)
  • Wages or salaries of supervisory and administrative personnel stationed at the site, with the owner's prior approval (Section 7.2.2)
  • Payments to subcontractors made in accordance with the subcontracts (Section 7.3)
  • Materials and equipment incorporated in the construction, with reasonable waste and spoilage (Section 7.4)
  • Temporary facilities, tools and equipment rental, debris removal and the site office (Section 7.5)
  • Premiums for the insurance and bonds the contract requires, sales and use taxes, permit fees and required testing (Section 7.6)

Article 8 lists what is not reimbursed, so it has to come out of the fee:

  • Salaries of personnel stationed at the contractor's principal office, except as Section 7.2 specifically provides
  • Expenses of the principal office and of offices other than the site office
  • Overhead and general expenses, except as expressly included in Article 7
  • The contractor's capital expenses, including interest on capital employed for the work
  • Costs due to the negligence of the contractor, its subcontractors and suppliers, or their failure to fulfill a specific responsibility of the contract
  • Any cost not specifically and expressly described in Article 7

Several items sit behind an approval. Where a cost is subject to the owner's prior approval, the contractor has to get it in writing before incurring the cost (Section 7.1.2). Rates and quantities of contractor-owned equipment need approval and total rental may not exceed the purchase price of a comparable item (Section 7.5.2). Trade discounts, rebates and refunds go to the owner as a credit against the cost of the work (Article 9).

04

What a guaranteed maximum price changes

A guaranteed maximum price, or GMP, puts a ceiling on a cost-plus contract. In A102 Section 5.2.1 the contractor guarantees that the contract sum will not exceed a stated amount, subject to additions and deductions by change order, and costs that would cause the GMP to be exceeded are paid by the contractor without reimbursement.

The GMP is an estimate with a guarantee attached, and the form makes room for what it rests on:

  • Alternates and allowances included in the GMP (Sections 5.2.2 and 5.2.3)
  • The assumptions the GMP is based on (Section 5.2.4)
  • Design development. Where the documents are expected to be developed further, the GMP already includes the cost of development that is consistent with them and reasonably inferable from them. Changes in scope, systems, or the kinds and quality of materials, finishes or equipment are not development; they are added by change order (Section 5.2.5)
  • Any bonus, cost savings or other incentive, written in at Section 5.1.7. The form does not set a savings split

Changes adjust the GMP by the methods in Article 7 of A201 (A102 Section 6.1), so change orders matter as much here as on a lump-sum job: a change that is built but never written up eats the room under the ceiling. For billing, the schedule of values allocates the whole GMP among the portions of the work, any contingency and the fee, and a line's share is not a separate guaranteed maximum for that line (Sections 12.1.5 and 12.1.5.2).

Under A133 the construction manager's GMP proposal is the sum of its estimate of the cost of the work, its contingency and its fee (Section 3.2.1). It comes with a written statement of its basis: the drawings and specifications it was priced from, the clarifications and assumptions, and the estimated cost organized by trade categories or systems (Section 3.2.3).

05

Without a GMP: the control estimate

Cost-plus without a ceiling still runs on an estimate. A103 Section 5.2 requires the contractor to submit a control estimate within 14 days of signing: the estimated cost of the work plus the fee. Section 5.2.2 says what it includes: the contract documents, a list of the contractor's assumptions, a statement of the estimated cost organized by trade categories or systems, a project schedule, and contingencies for further development of the design and construction.

The control estimate is then used to monitor the job. The contractor updates it with each application for payment as needed, and reports actual and remaining cost against it (Section 5.2.5). The owner's acceptance does not make it a guaranteed maximum price (Section 5.2.3). But if drawings, instructions or unanticipated conditions will significantly change the cost or the completion date compared with the control estimate, the contractor must notify the owner and architect in writing and not proceed with the affected work until it has written instructions (Section 6.3).

06

Getting paid, and audited

A cost-plus pay application is backed by records, not only by percentages. With each application the contractor submits payrolls, petty cash accounts, receipted invoices or invoices with check vouchers attached, and any other evidence the owner or architect requires (Section 12.1.4). Retainage is withheld as the agreement states.

The books are open. Article 11 gives the owner and its auditors access to the contractor's records and accounts, including job cost reports, subcontracts, subcontractor proposals and invoices, purchase orders and vouchers, and the records must be kept for three years after final payment. At the end the contractor submits a final accounting for the cost of the work. The owner has 30 days from receiving it to audit or to say it will not, and if the auditors substantiate less than the contractor claims, the contractor has 30 days from receiving the architect's final certificate for payment to request mediation before the auditors' figure becomes binding (Section 12.2.2).

Subcontracts follow the same logic: the contractor delivers the subcontract bids to the owner and architect (Section 10.1), and a subcontract may not be awarded on a cost-plus basis without the owner's prior written approval (Section 10.2).

07

What it means for the estimate

  • The estimate still decides the outcome. With a GMP, every dollar of cost above the ceiling is the contractor's. Without one, the control estimate is the yardstick the owner measures every pay application against.
  • Organize it the way the contract asks. Both the control estimate and the GMP proposal call for the estimated cost by trade categories or systems, which a quantity takeoff priced by CSI division gives you.
  • Write the assumptions, allowances and exclusions down. Under Section 5.2.5 the GMP already includes reasonably inferable design development, so a GMP priced from incomplete drawings needs its basis stated item by item. Know which type of estimate the drawings support.
  • Size the fee against Article 8. Home-office salaries, office expenses, general overhead and interest on capital are not reimbursed, so the fee has to carry them along with the profit.
  • Build general conditions to match Article 7. Site staff, the site office, temporary facilities, insurance and bond premiums are reimbursable, some only with the owner's prior approval.
  • Carry a contingency for the costs that are inside the GMP but not on any line, and show it as its own line in the schedule of values.

08

Mistakes that cost contractors money

  • Setting the fee as if it were only profit, then finding the home-office overhead has to come out of it.
  • Incurring a cost that needed the owner's prior approval, such as site supervisory staff or contractor-owned equipment, before getting the approval in writing.
  • Setting a GMP on early drawings without a written list of assumptions, so that later design development cannot be told apart from a change in scope.
  • Weak cost records. A cost that cannot be substantiated can be struck at the final audit.

09

A checklist before you sign

  • The fee: lump sum or percentage, and how it adjusts for changes
  • Articles 7 and 8 read line by line, with every cost that needs prior approval listed
  • With a GMP: the amount, the alternates, allowances and assumptions it rests on, and any savings clause
  • Without a GMP: the control estimate due 14 days after signing, and its update with each application
  • Job cost accounting set up to produce payrolls and receipted invoices with every application

10

Where we fit

We do not draft contracts or advise on them; a construction attorney does that. Our part is the estimate a cost-plus job runs on. Our construction cost estimates are built from a quantity takeoff and organized by CSI division with quantities, units, material and labor on every line, and we price change orders from revised drawings. The estimating fee is $180–$250 per estimator per day, by project complexity; see how our fees work. The sample estimates show the level of detail.

We estimate for general contractors and subcontractors across the United States and Canada. Send the drawings and we confirm the scope, fee and delivery date before work starts.

About the author

Navtej, Chief Estimator

B.Sc. in Civil Engineering, Master's in Quantity Surveying. Runs the estimating department, sets the standards every estimate is checked against and reviews high-stakes bids.

Meet the team

Questions contractors ask

What is a cost-plus contract?

A construction contract under which the owner pays the contractor the actual cost of the work, as the contract defines it, plus a fee for overhead and profit. The standard AIA forms are A102-2017, with a guaranteed maximum price, and A103-2017, without one.

What is a GMP contract?

A cost-plus contract with a ceiling. The contractor guarantees that the cost of the work plus the fee will not exceed a stated guaranteed maximum price, adjusted only by change order. Under AIA A102-2017 Section 5.2.1, costs above it are paid by the contractor without reimbursement.

What is the difference between cost-plus and lump sum?

Who carries the cost risk. Under a lump sum, or stipulated sum, contract the contractor is paid one fixed price whatever the work costs. Under cost-plus the owner reimburses the actual cost and pays a fee, so an overrun falls on the owner unless a guaranteed maximum price caps it.

What is cost plus fixed fee?

A cost-plus contract in which the fee is a lump sum set at the start instead of a percentage of cost. The fee does not rise when costs do; it is adjusted only when the work changes. On federal contracts a fee set as a percentage of cost is prohibited by FAR 16.102(c).

What costs are not reimbursed under a cost-plus contract?

Under Article 8 of AIA A102 and A103: salaries and expenses of the contractor's principal office, general overhead, capital expenses including interest, costs caused by the contractor's negligence, and any cost not expressly listed in Article 7. With a guaranteed maximum price, costs above the maximum are not reimbursed either.

Keep reading

Where this guide leads.

The services and sample estimates behind this guide, and the guides that pair with it.