Hanover Honda
Commercial · Hanover, MA
≈ $3.7M
Comprehensive bid-ready estimate package for an automotive facility covering GC, MEP, demolition, and site-related scopes.
- Estimate value
- ≈ $3.7M
- Project area
- Large automotive facility
Projects · Mixed-Use
California, USA
Delivered a detailed quantity takeoff and estimating package for concrete flatwork, footings, slab-related areas, trench drains, piers, and associated site infrastructure.

Trade
Concrete
Quantity lines
42
Project area
Mixed-use site package
Scope
Concrete and site development takeoff covering ramps, driveway work, slab areas, footings, piers, and drainage elements.
Concrete
Foundations
Drainage
Site Work
Estimating for this work
From the estimate · Divisions 03, 07, 31–33
Footings, grade beams, pilasters, slabs and an 11 ft shotcrete wall measured from the foundation plan, with rebar priced by bar size in pounds.
Full sizeItem
Measured
With waste
#5 rebar
Sheet S4 · 5% waste · 17,901.12 LBS with waste
17,048.69 LBS
(5'-6" x 1'-6") continuous footing, (5) #5 bars cont. T&B, #5 dowels @ 8" O.C.
Sheet S4 · 5% waste · 77.64 CY with waste
73.94 CY
(4'-0" x 3'-0") concrete grade beam, (8) #8 bars cont. T&B, #4 stirrups @ 8" O.C.
Sheet S4 · 5% waste · 13.53 CY with waste
12.89 CY
(2'-0" x 2'-0") concrete pilaster, 12'-8" high
Sheet S4 · 5% waste · 3.94 CY with waste
3.75 CY
(8") shotcrete wall, 4000 PSI, 11 ft high
Sheet S4 · 5% waste · 75.4 CY with waste
71.81 CY
(5") concrete slab, #4 @ 16" O.C. EW, 4" sand base, 15 mil vapor barrier
Sheet S4 · 5% waste · 3,708.6 SF with waste
3,532 SF
(6") concrete overpoured slab, #4 @ 16" O.C. EW
Sheet S4 · 5% waste · 391.65 SF with waste
373 SF
Tremco waterproofing coat, 11 ft walls
Sheet S4 · 10% waste · 3,093.2 SF with waste
2,812 SF
Excavation
Sheet S4 · 5% waste · 1,114.5 CY with waste
1,061.43 CY
(4") perforated drain pipe with gravel
Sheet S4 · 5% waste · 286.65 LF with waste
273 LF
Showing 10 of 42 quantity lines in this estimate. Prices removed.
Projects

Commercial · Hanover, MA
≈ $3.7M
Comprehensive bid-ready estimate package for an automotive facility covering GC, MEP, demolition, and site-related scopes.

Residential · Carlsbad, CA
$436,725
Residential site and retaining wall estimate covering grading, excavation, drainage, waterproofing, and wall-related scope.

Commercial · Costa Mesa, CA
Tenant improvement estimating package for a high-end fitness facility with structural steel and architectural metal scope.
2930 Carleton St
Send the drawings, the scope and the bid date. We reply with a quote within 30 minutes during business hours.