Guide · Bidding

What are performance and payment bonds?

A performance bond is a surety's guarantee to the owner that the contract will be performed. A payment bond is its guarantee that the subcontractors and suppliers on the job will be paid. Here is where the two show up in the contract, what the surety does when each is called, the notice deadlines that decide a payment bond claim, and where the premium belongs in the estimate.

  • What each bond guarantees, under AIA A312 and the federal rules
  • The 90-day notice and one-year deadlines on a payment bond
  • Where the premium goes in the estimate and in change orders

Written by

Navtej, Chief Estimator

B.Sc. in Civil Engineering, Master's in Quantity Surveying. Runs the estimating department at E 4 Estimators.

  • 01

    Published November 11, 2026

  • 02

    10 min read

01

The short answer

Both are three-party guarantees furnished for the contract itself, not with the bid. The contractor is the principal, the owner is the obligee, and a surety stands behind the contractor. The performance bond protects the owner: if the contractor defaults and is terminated, the surety arranges completion or pays the owner under the terms of the bond. The payment bond protects the people below the contractor: a subcontractor or supplier who is not paid for labor, materials or equipment used on the job can claim against it.

They are separate bonds, normally issued together. The standard US forms are the two parts of AIA Document A312-2010, Performance Bond and Payment Bond; in Canada they are CCDC 221 and CCDC 222. On federal construction the Bonds statute at 40 U.S.C. 3131 to 3134, still widely called the Miller Act, requires both, and FAR 28.102-1 applies it to any construction contract over $150,000. Neither is the bid bond, which only guarantees that the low bidder will sign the contract and furnish these two.

02

Where the bonds show up

On a private job built on AIA documents the requirement starts in AIA A701-2018, Instructions to Bidders. Section 7.1.1 calls for the bonds when the bidding documents stipulate them. Section 7.1.4 sets the penal sum of each at the contract sum unless stated otherwise, Section 7.2.1 has them delivered not later than three days after the contract is signed, and Section 7.2.2 writes them on A312 unless the documents provide otherwise. In the contract itself, AIA A201-2017 Section 11.1.2 requires the contractor to provide surety bonds of the types, penal sums and terms the contract documents require, from a company lawfully authorized to issue surety bonds where the project is located.

On federal work the clause is FAR 52.228-15, Performance and Payment Bonds, Construction. Each bond is 100 percent of the original contract price, on Standard Form 25 and Standard Form 25-A, and FAR 28.102-2 adds that the payment bond is never less than the performance bond. The executed bonds are due within the time the solicitation sets and in any event before work starts. Corporate sureties must appear on Treasury Department Circular 570. Between $35,000 and $150,000 the contracting officer picks alternative payment protections instead, such as a payment bond or an irrevocable letter of credit (FAR 28.102-1).

State and local public work comes under the state's own bond statute, not the federal one, and its threshold and notice deadlines can differ. Read the statute for the project's state, because A312 Performance Bond Section 13 and Payment Bond Section 14 say that a bond furnished to meet a legal requirement is read as a statutory bond: anything in the form that conflicts with the statute drops out.

03

How a performance bond works

Under the A312 Performance Bond the surety owes nothing while the contractor performs. Section 3 sets what the owner must do before the surety's obligation arises, provided the owner itself is not in default: give notice to the contractor and the surety that it is considering declaring a contractor default; declare the default, terminate the contract and notify the surety; and agree to pay the balance of the contract price to the surety or to the completing contractor. The first notice can lead to a conference. If the owner does not ask for one, the surety may within five business days, and it is held within ten business days of the surety receiving the notice unless the owner agrees otherwise.

Once those conditions are met, Section 5 gives the surety four choices, at its own expense:

  • Arrange for the contractor to complete the contract, with the owner's consent (Section 5.1)
  • Complete the contract itself, through its agents or independent contractors (Section 5.2)
  • Obtain bids from qualified contractors acceptable to the owner, arrange a new bonded contract with one of them, and pay the owner's damages above the balance of the contract price (Section 5.3)
  • Waive those rights and, after investigation, either pay the owner the amount it determines it owes or deny liability in whole or in part, with reasons (Section 5.4)

Section 7 lists what the surety answers for when it takes over: correction of defective work and completion, the additional legal, design professional and delay costs the default causes, and liquidated damages, or actual delay damages where the contract states none. Section 8 limits the surety's liability to the amount of the bond when it acts under Section 5.1, 5.3 or 5.4. If the surety does not move with reasonable promptness, Section 6 puts it in default seven days after a further written notice from the owner. Any suit on the bond must start within two years of the declaration of default, the contractor ceasing work, or the surety's refusal to perform, whichever comes first (Section 11). No one but the owner has a right of action on it (Section 9).

The lesson for a contractor is that a performance bond is not insurance for the contractor. Only the owner can claim on it, and the unpaid balance of the contract price, retainage included, goes to the surety or the completing contractor to finish the job (Section 3.3).

04

How a payment bond works

The payment bond is the one subcontractors and suppliers use, and it runs on deadlines. Under the A312 Payment Bond a claimant is anyone with a direct contract with the contractor, or with one of the contractor's subcontractors, to furnish labor, materials or equipment for the job; the definition takes in rental equipment and utilities used on the work (Section 16.2). The table sets the A312 steps beside the federal statute.

Claimant with a direct contract with the primeAIA A312-2010 Payment BondSends a written Claim to the surety (Section 5.2)Federal work (40 U.S.C. 3133)May sue on the bond if not paid in full within 90 days after its last labor or material
Claimant under a subcontractorAIA A312-2010 Payment BondWritten notice of non-payment to the contractor within 90 days after last furnishing labor, materials or equipment, stating the amount and the party supplied; then a Claim to the surety (Section 5.1)Federal work (40 U.S.C. 3133)Written notice to the contractor within 90 days of its last labor or material, stating the amount and the party supplied, delivered by a means that gives third-party proof of delivery
Surety's responseAIA A312-2010 Payment BondAn answer within 60 days of receiving the Claim, stating what is undisputed and why the rest is challenged, and payment of the undisputed amount (Section 7)Federal work (40 U.S.C. 3133)Not set by the statute
Deadline to sueAIA A312-2010 Payment BondOne year from sending the Claim, or from the last labor or materials furnished by anyone under the construction contract, whichever is first (Section 12)Federal work (40 U.S.C. 3133)One year after the claimant's own last labor or material, in the name of the United States, in the US District Court for a district where the contract was to be performed

A Claim under A312 is a defined document. Section 16.1 lists eight items, among them the claimant's name, the party it worked for, a copy of the agreement or purchase order, a description of what was furnished, the date last furnished, the amount earned, payments received and the amount unpaid. If the surety misses its 60 days it does not lose its defenses, but it owes the reasonable attorney's fees the claimant then incurs to recover what is found to be due (Section 7.3).

Getting a copy of the bond is a right. A201 Section 11.1.3 and A312 Payment Bond Section 15 require the contractor to furnish one to anyone who appears to be a potential beneficiary. On federal work the contracting officer gives a subcontractor or supplier the surety's name and address on request (FAR 28.106-6). And under 40 U.S.C. 3133(c) a waiver of the right to sue on a federal payment bond is void unless it is in writing, signed, and made after the claimant has furnished labor or material.

05

What the bonds mean for the estimate

The bonds are a cost, and the bidding documents decide where it sits. A701 Section 7.1.2 puts the cost in the bid when the documents stipulate bonds; when the owner asks for them after bids are in, the cost is added to the bid in setting the contract sum.

  • Carry the premium on its own line if the bid form has one, otherwise in general conditions with the insurance. The two bonds are usually issued together for one premium, so price them as one item, from your surety agent's quote.
  • Remember that the penal sum is the whole contract price, markups included: the contract sum under A701 and 100 percent of the contract price on federal work. Ask your agent for the premium on the final bid figure, not on cost.
  • Add it to change orders. A201 Section 7.3.4.4 counts premiums for bonds and insurance directly related to the change among the costs when a construction change directive is priced, and on federal work the Government may require added bond protection when the price goes up, generally 100 percent of the increase (FAR 52.228-15). See what a change order is.
  • If you are a subcontractor asked for bonds, price them the same way. A312 provides for a bond on a subcontract (Performance Bond Section 15, Payment Bond Section 17), reading Contractor as subcontractor and Owner as contractor.

The estimate matters to the surety too. A performance bond puts the surety behind the price, and a job bid below its cost is hard to finish. A complete quantity takeoff and a checked cost estimate are what make the number one you can finish the job for.

06

Mistakes that cost contractors money

  • Leaving the premium out of the bid, or out of the change order pricing as the contract grows.
  • A second-tier subcontractor or supplier missing the 90-day notice to the prime contractor. The notice runs from the last day labor or material was furnished, not from the invoice date.
  • Sending a letter to the surety that is not a Claim. Under A312 the surety's 60 days start only when it receives a Claim with the Section 16.1 contents.
  • Waiting past the one-year deadline to sue while negotiations drag on. Under A312 the year can run from the last work by anyone on the project, not only your own.

07

A checklist for bonded work

  • Before bidding: whether the bonds are stipulated, on which forms, in what penal sum, and when they are due
  • The premium quote from your surety agent, and where the bid form wants it
  • As a subcontractor or supplier: a copy of the payment bond at the start of the job, with the surety's name and address
  • The date you last furnished labor or material, recorded for every project and kept current
  • Notice and claim deadlines in the calendar: 90 days for notice, one year to sue, or the state statute's dates on state and local public work
  • The bond premium on every change order that raises the contract price

08

Where we fit

We do not write bonds or advise on claims; a surety agent and a construction attorney do that. Our part is the number the bonds stand behind. Our construction cost estimates are organized by CSI division with quantities, units, material and labor on every line, and we price change orders from revised drawings, so the contract price and each change to it can be checked. The estimating fee is $180–$250 per estimator per day, by project complexity; see how our fees work. The sample estimates show the level of detail.

We estimate for general contractors and subcontractors across the United States and Canada. Send the drawings and we confirm the scope, fee and delivery date before work starts.

About the author

Navtej, Chief Estimator

B.Sc. in Civil Engineering, Master's in Quantity Surveying. Runs the estimating department, sets the standards every estimate is checked against and reviews high-stakes bids.

Meet the team

Questions contractors ask

What is a performance bond in construction?

A surety's guarantee to the owner that the contractor will perform the construction contract. If the contractor defaults and the owner terminates it, the surety arranges completion or pays the owner under the terms of the bond. The standard US form is the AIA A312-2010 Performance Bond.

What is a payment bond?

A surety's guarantee that the subcontractors and suppliers who furnish labor, materials or equipment for the job will be paid. A claimant who is not paid gives the notices the bond or the statute requires and claims against the surety instead of the owner.

What is the difference between a performance bond and a payment bond?

Who is protected. The performance bond runs to the owner and covers completion of the work; under A312 only the owner can claim on it. The payment bond covers the subcontractors and suppliers under the contractor. They are separate bonds, usually issued together for one premium.

What is the Miller Act?

The federal statute, now 40 U.S.C. 3131 to 3134, that requires a performance bond and a payment bond on federal construction contracts. FAR 28.102-1 applies it to contracts over $150,000. It gives unpaid subcontractors and suppliers the right to sue on the payment bond, with a 90-day notice for those under a subcontractor and a one-year deadline to sue.

How much is a performance bond?

The bond amount is set by the contract documents: the contract sum under AIA A701 unless stated otherwise, and 100 percent of the original contract price on federal work. What it costs you is the premium your surety quotes, which belongs in the bid and in each change order that raises the price.

Keep reading

Where this guide leads.

The services and sample estimates behind this guide, and the guides that pair with it.

Next bid

Bid due soon? Send the drawings.

Send the drawings, the scope and the bid date. We reply with a quote within 30 minutes during business hours.