Guide · Estimating basics

UniFormat: the elemental format for early estimates, and how it maps to MasterFormat.

UniFormat sorts a building by elements, the parts that do a job whatever they are made of: foundations, exterior walls, roofing, plumbing, lighting. Owners and design teams use it for budgets before products are chosen, while trades bid by MasterFormat. Here is how the classification is built, how an elemental budget is measured and priced, where items get lost on the boundaries, and how a UniFormat budget becomes a bid.

  • The ASTM and CSI versions, and the lettered groups
  • How an elemental budget is measured and checked
  • Mapping a UniFormat budget to MasterFormat trades

Written by

Navtej, Chief Estimator

B.Sc. in Civil Engineering, Master's in Quantity Surveying. Runs the estimating department at E 4 Estimators.

  • 01

    Published November 25, 2026

  • 02

    9 min read

01

The short answer

UniFormat organizes a building's cost by elements. ASTM defines elements as major components common to most buildings that usually perform a given function, regardless of the design specification, construction method or materials used. Foundations, exterior walls, roof coverings, plumbing fixtures and lighting are elements. A brick cavity wall and a metal panel wall on studs are both B2010 Exterior Walls: they differ in quality and cost, not in where they sit in the estimate.

It is built for the stage before products are chosen. An early budget cannot be priced by specification section, because the sections are not written yet, but it can be priced by element: so many square feet of exterior wall at a given quality, so many of roof. Once the drawings reach construction documents the work is bought by trade, and the estimate moves to MasterFormat. ASTM itself says UNIFORMAT II is unsuitable for preparing trade estimates.

02

UNIFORMAT II, UniFormat 2010 and the original

The original UNIFORMAT was a common elemental format agreed between the American Institute of Architects and the General Services Administration, building on a format Hanscomb Associates developed for the AIA in 1973. In 1989 ASTM's building economics subcommittee started a standard based on it, and ASTM E1557, Standard Classification for Building Elements and Related Sitework, UNIFORMAT II, was approved in 1993. The edition in force is E1557-09, reapproved in 2024. It has three levels, with a suggested fourth in an appendix, and covers building-related sitework but not major civil works.

CSI and CSC publish their own UniFormat, now in its 2010 edition. CSI says its primary use is as a format for estimators to present cost estimates during schematic design, and that it is also used for performance specifications and preliminary project descriptions. Its master list gives the related MasterFormat numbers for each title. CSI also sells a transition matrix between its 2010 and 1998 editions, ASTM E1557, and the GSA and NAVFAC versions. Several versions are in use, so before you map codes, find out which one the owner's cost plan or the design team's documents follow.

Canada has its own elemental classification from the Canadian Institute of Quantity Surveyors (CIQS), first issued in 1972, with different groups and codes. On a Canadian project, ask which format the cost plan uses before you compare numbers against it.

03

The levels and the lettered groups

Level 1 holds the major groups, Level 2 splits each into group elements, and Level 3 into individual elements. The codes build up: B is Shell, B20 is Exterior Enclosure, B2010 is Exterior Walls. The table shows the 1997 edition of E1557 as printed in NIST's 1999 report on UNIFORMAT II, the latest full list that is free to read. The current ASTM and CSI editions are sold.

A SubstructureLevel 2 group elementsA10 Foundations, A20 Basement ConstructionExamples at Level 3A1010 Standard Foundations, A1020 Special Foundations, A1030 Slab on Grade, A2020 Basement Walls
B ShellLevel 2 group elementsB10 Superstructure, B20 Exterior Enclosure, B30 RoofingExamples at Level 3B1010 Floor Construction, B2010 Exterior Walls, B2020 Exterior Windows, B3010 Roof Coverings
C InteriorsLevel 2 group elementsC10 Interior Construction, C20 Stairs, C30 Interior FinishesExamples at Level 3C1010 Partitions, C1020 Interior Doors, C1030 Fittings, C3020 Floor Finishes
D ServicesLevel 2 group elementsD10 Conveying, D20 Plumbing, D30 HVAC, D40 Fire Protection, D50 ElectricalExamples at Level 3D2010 Plumbing Fixtures, D3040 Distribution Systems, D4010 Sprinklers, D5020 Lighting and Branch Wiring
E Equipment and FurnishingsLevel 2 group elementsE10 Equipment, E20 FurnishingsExamples at Level 3E1010 Commercial Equipment, E2010 Fixed Furnishings
F Special Construction and DemolitionLevel 2 group elementsF10 Special Construction, F20 Selective Building DemolitionExamples at Level 3F2010 Building Elements Demolition, F2020 Hazardous Components Abatement
G Building SiteworkLevel 2 group elementsG10 Site Preparation, G20 Site Improvements, G30 Site Mechanical Utilities, G40 Site Electrical Utilities, G90 Other Site ConstructionExamples at Level 3G1030 Site Earthwork, G2020 Parking Lots, G3020 Sanitary Sewer, G4020 Site Lighting

Markups are not elements. E1557 classifies building elements only, so the estimate summary NIST proposes carries the design allowance, the general contractor's overhead and profit, and the inflation allowance on separate Z lines below the elements. CSI's 2010 edition has a Z General group of its own.

04

How an elemental estimate is built

Each element is priced as a quantity of the element times a rate for it. NIST's report gives the units: standard foundations in square feet of footprint, roof coverings and rainwater drainage in square feet of roof, partitions in square feet of partition, cooling in tons of refrigeration. The rate can come three ways: an elemental rate from past projects, the sum of the assemblies that make up the element, or the sum of its components. One estimate can mix all three, element by element.

An elemental cost carries material, labor and the subcontractor's overhead and profit. The general contractor's overhead and profit, the design allowance and escalation sit below the elements. The design allowance is for items the design has not shown yet. It is set at programming, should reach zero by the end of construction documents, and does not cover scope changes, which need more money or a change to the program.

The summary is read through ratios: each element's cost per square foot of gross floor area, its own unit rate, and its quantity per square foot of floor area, such as exterior wall area to floor area. Most of them hang on gross floor area, so the area must be measured the same way as on the projects you compare against.

05

Where you will meet it

  • Owner and design-team budgets at programming, schematic design and design development. ASTM lists elemental cost plans and design-to-cost targets among its uses.
  • Preliminary project descriptions. At schematic design the design team describes each system by element, so the budget and the description share the same codes.
  • Design-build and negotiated work, where the contractor prices the job before the drawings are finished and updates the price with each issue. That is the work our design-build pricing support covers.

06

From a UniFormat budget to a MasterFormat bid

Elements and trades cut the building in different directions: one element is built by several trades, and one trade works in several elements. CSI's list of related MasterFormat numbers helps, but the split is made on the drawings. Typical splits:

A10 FoundationsWhere the work is bought in MasterFormat03 Concrete for footings, pile caps and slab on grade; 31 Earthwork for excavation, backfill and piles; 07 for perimeter insulation and dampproofing. Concrete estimating
B2010 Exterior WallsWhere the work is bought in MasterFormat04 Masonry, 05 Metals for cold-formed framing, 06 for sheathing, 07 for insulation, air barrier and sealants, 09 for gypsum board on the back-up. Masonry estimating
B2020 Exterior WindowsWhere the work is bought in MasterFormat08 Openings for windows, storefronts and curtain wall; lintels, sills and flashing at openings may sit in 04, 05 or 07
B3010 Roof CoveringsWhere the work is bought in MasterFormat07 Thermal and Moisture Protection for membrane, roof insulation, flashing, gutters and downspouts. Roofing estimating
C1030 Fittings and C30 Interior FinishesWhere the work is bought in MasterFormat10 Specialties for toilet partitions, accessories, lockers and signage; 09 Finishes for the wall, floor and ceiling finishes
D ServicesWhere the work is bought in MasterFormat14 Conveying Equipment, 21 Fire Suppression, 22 Plumbing, 23 HVAC, 25 Integrated Automation, 26 Electrical, 27 Communications, 28 Electronic Safety and Security. MEP estimating
G Building SiteworkWhere the work is bought in MasterFormat31 Earthwork, 32 Exterior Improvements, 33 Utilities, with site lighting under 26. Sitework estimating

The conversion is where budgets lose scope. One element line becomes five or six trade packages, and each has to pick up its share. Check that every element has a home in a trade package and that boundary items are carried once. Our MasterFormat guide lists the lines between divisions that we check on every set.

07

Where items sit on the boundaries

These follow the inclusion and exclusion lists for the 1997 edition in NIST's report. Check them against the version your project uses.

  • Curtain walls and storefronts are B2020 Exterior Windows, not B2010 Exterior Walls.
  • Columns and beams in an exterior wall are Superstructure (B10), not the wall.
  • Finishes on the inside face of an exterior wall are C3010 Wall Finishes; the back-up framing and wallboard stay in B2010.
  • Gutters and downspouts are B3010 Roof Coverings; roof drains and their piping are D2040 Rain Water Drainage.
  • Water heaters are D2020 Domestic Water Distribution, not plumbing fixtures.
  • Outdoor transformers are G4010 Electrical Distribution. Lights on the building are D5020; site lighting is G4020.
  • Pile caps are A1010 Standard Foundations; the piles are A1020 Special Foundations.
  • Demolishing a whole building is G1020 Site Demolition; demolition inside a building that stays is F20.

08

Mistakes that cost money

  • Bidding from a UniFormat budget. An elemental rate is an average for a type and quality of element. A bid needs quantities measured from the drawings and priced by trade.
  • Comparing against data that splits elements differently. A curtain wall carried in walls on one project and in windows on another makes both rates wrong.
  • Measuring gross floor area differently from the reference projects, which shifts every cost per square foot.
  • Carrying the design allowance into the final estimate, or spending it on scope changes.
  • Burying markups inside element rates. Keep overhead and profit, the design allowance and escalation on their own lines, or two budgets cannot be compared.
  • Losing scope in the conversion to trade packages, especially items that sat inside one element but belong to a trade that also works elsewhere: lintels, flashing, blocking, firestopping.

09

A checklist for a UniFormat budget

  • Which version: ASTM E1557, CSI/CSC UniFormat 2010, CIQS, or the owner's own list.
  • Which level the budget is priced at, Level 2 or Level 3.
  • Gross floor area, footprint, roof area and exterior wall area measured and stated, with the method.
  • Each element shown with its quantity, unit, rate and cost per square foot of floor area.
  • The system or quality level assumed for each element written next to it.
  • Building and sitework summarized separately.
  • Design allowance, overhead and profit, and escalation on their own lines.
  • Exclusions listed.
  • At bid time, every element mapped to a trade package and each boundary item assigned once.

10

Where we fit

Our construction cost estimates are priced by CSI division, which is MasterFormat, because that is how the work is bought. They are built from a quantity takeoff measured from your drawings, with quantities, units, material and labor on every line. For design-build teams we prepare early budget estimates and update them as the design develops, with notes on what changed the price between drawing issues. The estimating fee is $180–$250 per estimator per day, by project complexity; see how our fees work. The sample estimates show the layout, and our guide to types of construction estimates explains which estimate fits each design stage.

We estimate for general contractors and subcontractors across the United States and Canada. Send the drawings and we confirm the scope, fee and delivery date before work starts.

About the author

Navtej, Chief Estimator

B.Sc. in Civil Engineering, Master's in Quantity Surveying. Runs the estimating department, sets the standards every estimate is checked against and reviews high-stakes bids.

Meet the team

Questions contractors ask

What is UniFormat?

A classification that organizes a building by elements, the major components that perform a function whatever they are made of, such as foundations, exterior walls, roofing and lighting. ASTM publishes it as UNIFORMAT II (E1557); CSI and CSC publish UniFormat 2010. It is used mainly for budgets before products are chosen.

What is the difference between UniFormat and MasterFormat?

UniFormat sorts by element: the part of the building and what it does. MasterFormat sorts by work result: the way work is specified and bought. One UniFormat exterior wall line becomes masonry, framing, insulation and gypsum board in MasterFormat. Early budgets use UniFormat; specifications, bids and detailed estimates use MasterFormat.

What are the UniFormat Level 1 categories?

A Substructure, B Shell, C Interiors, D Services, E Equipment and Furnishings, F Special Construction and Demolition, and G Building Sitework. CSI's 2010 edition calls G Sitework and adds Z General.

What is UNIFORMAT II?

ASTM's version, E1557, Standard Classification for Building Elements and Related Sitework. It was approved in 1993, built on the original UNIFORMAT of the AIA and GSA. The current edition is E1557-09, reapproved in 2024.

Can you bid a job from a UniFormat estimate?

Not safely. Elemental rates are averages for a type and quality of element, and ASTM says UNIFORMAT II is unsuitable for preparing trade estimates. A bid needs quantities measured from the construction documents and priced by trade, which means a MasterFormat estimate.

Keep reading

Where this guide leads.

The services and sample estimates behind this guide, and the guides that pair with it.

Next bid

Bid due soon? Send the drawings.

Send the drawings, the scope and the bid date. We reply with a quote within 30 minutes during business hours.