What are as-built drawings?

As-built drawings are the contract drawings marked up by the contractor to show what was actually built: the field changes, the real locations of concealed work and the changes made by change orders and RFI responses. Here is who prepares them, how they differ from record drawings, what the specification expects on them, what they cost to keep, and how to hand over a set that is accepted the first time.

  • As-built, record and measured drawings: who prepares each
  • What the contract and Section 01 78 39 expect on the set
  • What to carry in the bid, and how to close out without a rework

Written by

Navtej, Chief Estimator

B.Sc. in Civil Engineering, Master's in Quantity Surveying. Runs the estimating department at E 4 Estimators.

  • 01

    Published November 18, 2026

  • 02

    8 min read

01

The short answer

As-built drawings, often just called as-builts, are a set of the contract drawings that the contractor marks up during construction to show the work as it was actually installed. Where a pipe was rerouted, a footing went deeper or a change order moved a wall, the as-builts show the real condition, not the designed one. The marks are usually made in red, which is why the working set is also called the redlines.

The owner uses them for the life of the building: to find a buried line before digging, to plan a renovation, to maintain equipment. For the contractor they are a closeout deliverable, and a set that is late or incomplete can hold up the end of the job.

02

As-built, record and measured drawings

The three terms are often mixed up. A joint best practice statement from the Ontario Association of Architects and the Ontario General Contractors Association (2010) separates them this way:

Prepared byAs-built drawingsThe contractor, as it buildsRecord drawingsThe architect, when contracted to do soMeasured drawingsWhoever is engaged to measure the building
Based onAs-built drawingsField data: actual locations and changes to the contract documentsRecord drawingsThe original drawings, changes known to the architect and the contractor's as-builtsMeasured drawingsOn-site measurements of an existing building or space
Typical useAs-built drawingsTurned over at completion as the contractor's recordRecord drawingsThe owner's clean set for facility management and later workMeasured drawingsA base for additions, alterations or lease areas

The AIA forms draw the same line. AIA B101-2017, the owner-architect agreement, lists measured drawings, as-designed record drawings and as-constructed record drawings as separate supplemental services (Sections 4.1.1.3, 4.1.1.15 and 4.1.1.16). They are not included in the architect's basic services, so the architect prepares them only when the agreement assigns them.

Many specifications use the words loosely and call the contractor's marked-up set the record drawings. Go by what the section asks you to deliver, not by its title.

03

What the contract requires

AIA A201-2017 sets the duty in Section 3.11 without using the word as-built. The contractor keeps the contract documents at the site, including change orders, construction change directives and other modifications, in good order and marked currently to indicate field changes and selections made during construction, together with the approved shop drawings, product data and samples. They may be electronic or paper, they are available to the architect and owner, and they are delivered to the architect for the owner upon completion as a record of the work as constructed.

Two words in that clause do the work. Marked currently means as the job goes, not from memory in the last week. And the set is the contract documents plus the approved submittals, not the drawings alone.

The detail is in Division 01 of the specifications, usually Section 01 78 39, Project Record Documents. It covers record drawings, record specifications and record product data, and it says what to mark, in what format and when to hand it over. Read it before you bid: owners edit this section heavily.

04

What goes on the as-builts

The rule is to mark the actual installation wherever it varies from what was shown originally. Two published owner standards for Section 01 78 39, the University of Southern California's (2016) and Northwestern University's (2019), list nearly the same items:

  • Dimensional changes, and revisions to details
  • Depths of foundations below the first floor
  • Locations and depths of underground utilities
  • Locations of utilities concealed inside the building
  • Revisions to the routing of piping and conduits, and to electrical circuitry
  • Actual equipment locations, and duct size and routing
  • Changes made by change order or construction change directive, and by the architect's written orders
  • Details that were not on the original contract drawings
  • Field records for variable and concealed conditions
  • Work that the drawings show only schematically

Both sections tell the contractor to give particular attention to concealed elements that would be difficult to identify or measure later. Underground and in-wall work is where an as-built earns its keep, and it is the one thing nobody can go back and check.

05

Keeping them during the job

  • Keep one clean set of prints, or one controlled PDF set, for as-builts only. Add new and revised sheets to it as modifications are issued.
  • Have the people who did the work supply the data. Both university sections look to whoever obtained the record data, installer or subcontractor, to prepare the markup or provide the information for it.
  • Record before you cover. Northwestern's section says to record and check the markup before enclosing concealed installations; USC's says not to permanently conceal any work until the information is recorded.
  • Mark in red. Both sections call for erasable red pencil, with other colors to separate different categories of work at the same location.
  • Reference the source. Note the change order, construction change directive or RFI number beside the change it caused.
  • Mark whichever sheet shows the condition better, the contract drawing or the shop drawing, and cross-reference the other.
  • Tie locations to something permanent. USC's section asks for underground utilities referenced to permanent surface improvements, and concealed utilities to visible, accessible features of the building.

Expect the set to be checked before the end. USC's section has the owner review the as-builts monthly and lets it withhold the monthly payment if they are not maintained. Where your contract says something similar, bring the set up to date before each pay application.

06

From redlines to the closeout set

What you hand over depends on the section. Some owners accept the marked-up prints, or scans of them. Others want the changes drafted into the drawing files. Northwestern's section has the contractor review the marked-up prints with the architect immediately before the substantial completion inspection and then, when authorized, prepare a full set of corrected digital data files in the same software as the original contract drawings. USC's asks for a hard copy set and a digital set at substantial completion and permits scans of the redlined originals; its design team then updates the drawing files.

Where drafted files are required, the usual expectations are:

  • One electronic file for each sheet of the contract drawings, named with the sheet identification
  • Each sheet identified and dated, with the designation the section asks for, such as PROJECT RECORD DRAWINGS or AS-BUILT DRAWINGS
  • The project name, the date and the names of the architect and the contractor
  • Every sheet submitted, whether or not anything on it changed
  • A transmittal listing the documents; USC's section also asks for a signed certification that each one is complete and accurate

Uncertain points go to the architect to resolve. They are not settled by the drafter's guess.

07

What it means for the estimate

As-builts cost money, and the money belongs in the bid. The Ontario joint statement says so directly: where the contract documents require more accuracy in some areas of the as-builts, the contractor should include adequate monies for the work in its tender price, and a contractor asked to convert as-builts to CAD should be compensated for it and should raise the question before the tender closes.

  • Read Section 01 78 39 at bid time and list the deliverables: marked prints only, or drafted DWG or Revit files, a record model, record specifications and product data.
  • Price the field time to keep the set current, and any survey needed to locate underground utilities.
  • Price the drafting if digital files are required, in house or bought out.
  • Carry it with your general conditions or Division 01 costs, where closeout documents are normally priced.
  • Pass the requirement down. Each subcontract should say what the trade marks up, in what format and by when.

08

Mistakes that cost money

  • Building the as-builts from memory at the end of the job. Concealed work can no longer be measured.
  • Covering underground or in-wall work before its location is recorded.
  • No as-built requirement in the subcontracts, so the mechanical, electrical and plumbing redlines never arrive.
  • Bidding marked-up prints when the section calls for drafted CAD or Revit files.
  • Marks with no source, so nobody can tell an approved change from a field fix.
  • Leaving change orders and RFI responses off the set because they are filed somewhere else.

09

A checklist for the as-built set

  • Section 01 78 39 read, and the deliverables, formats and due dates listed
  • One as-built set assigned to one person, updated as the work goes
  • Concealed and underground work recorded before it is covered
  • Each change marked with its change order, directive or RFI number
  • Subcontractor redlines collected before the trades leave the site
  • Every sheet identified, dated and labelled as the section requires
  • Digital files, where required, in the software and naming the owner asked for

10

Where we fit

We draft as-built drawings for contractors closing out a project. You send the drawing set, the field redlines and the RFI responses and change orders that changed the work; scans or photos of marked-up sheets are fine. We draft them into a clean set in AutoCAD or Revit, with a PDF set for closeout and a change log that records the source of each change. Unclear redlines come back as a list of questions instead of being guessed, and the original sheet numbers are kept.

We also prepare shop drawings by trade and construction drawings. Send the redlines and we confirm the fee and the delivery date before any drafting starts.

About the author

Navtej, Chief Estimator

B.Sc. in Civil Engineering, Master's in Quantity Surveying. Runs the estimating department, sets the standards every estimate is checked against and reviews high-stakes bids.

Meet the team

Questions contractors ask

What are as-built drawings?

Drawings that show a project as it was actually constructed. The contractor marks up the contract drawings during the job to record field changes, the real locations of concealed and underground work, and the changes made by change orders and RFI responses.

Who prepares as-built drawings?

The contractor, with each subcontractor marking up its own trade. Under AIA A201-2017 Section 3.11 the contractor keeps the contract documents at the site marked currently to indicate field changes and delivers them at completion as a record of the work as constructed.

What is the difference between as-built drawings and record drawings?

As-built drawings are the contractor's marked-up set. Record drawings are prepared by the architect, when contracted to do so, from the original drawings, the changes the architect knows of and the contractor's as-builts. Many specifications use the two names interchangeably, so check what the section asks for.

When are as-built drawings due?

When the specification says, usually in Section 01 78 39 or the closeout section. The owner standards quoted in this guide set them at or just before substantial completion, and A201-2017 has the record set delivered upon completion of the work.

What does redline mean on as-built drawings?

Redlines are the marks, usually in red pencil or red PDF markup, that show where the installed work differs from the drawing. A redlined set is the working as-built; some owners accept it as it is, and others require the redlines to be drafted into CAD or Revit files.

Keep reading

Where this guide leads.

The services and sample estimates behind this guide, and the guides that pair with it.

Next bid

Bid due soon? Send the drawings.

Send the drawings, the scope and the bid date. We reply with a quote within 30 minutes during business hours.