Guide · Contracts

Design-bid-build vs design-build vs CM at risk: how each delivery method changes the estimate.

A project delivery method decides who signs with whom, when the builder joins the team and when the price is fixed. Design-bid-build prices finished drawings in a bid. Construction manager at risk joins during design, estimates each drawing issue and then offers a guaranteed maximum price. Design-build puts design and construction in one contract and prices the job on a preliminary design. Here is how each method changes the estimate, what it asks of subcontractors and where the money gets lost.

  • Who holds the contracts in each method
  • When the price is set, and on which drawings
  • What each method asks of the estimate

Written by

Navtej, Chief Estimator

B.Sc. in Civil Engineering, Master's in Quantity Surveying. Runs the estimating department at E 4 Estimators.

  • 01

    Published November 26, 2026

  • 02

    9 min read

01

The short answer

A delivery method is the way an owner contracts for design and construction. The federal acquisition rules give the plainest definitions. Design-bid-build is "the traditional delivery method where design and construction are sequential and contracted for separately with two contracts and two contractors." Design-build is "combining design and construction in a single contract with one contractor" (FAR 36.102). Construction manager at risk, CM at risk or CMAR, sits between them: the owner still hires the architect separately, but brings the builder in during design to advise, estimate and then guarantee a maximum price.

For an estimator the difference is timing. The method decides how much of the design exists when your number becomes a commitment, and that decides how the estimate is built, what it carries for the unknowns and who reads it.

02

The three methods side by side

Contracts the owner signsDesign-bid-buildArchitect first, then contractorCM at riskArchitect, then a construction manager during designDesign-buildOne, with the design-builder
When the builder joinsDesign-bid-buildAfter design, at bid timeCM at riskDuring designDesign-buildAt the start, before design
Price basisDesign-bid-buildStipulated (lump) sum on finished documentsCM at riskCost of the work plus a fee, capped by a GMPDesign-buildStipulated sum, or cost plus a fee with or without a GMP, on a preliminary design
Who designsDesign-bid-buildOwner's architectCM at riskOwner's architectDesign-buildDesign-builder
Where trade contractors bidDesign-bid-buildTo general contractorsCM at riskTo the CM, package by packageDesign-buildTo the design-builder
AIA agreementDesign-bid-buildA101-2017CM at riskA133-2019 (A134-2019 without a GMP)Design-buildA141-2014
CCDC contract (Canada)Design-bid-buildCCDC 2-2020CM at riskCCDC 5B-2025Design-buildCCDC 14-2026

03

Design-bid-build: pricing finished documents

The owner's architect finishes the drawings and specifications, the job goes out to bid, and the contract is signed for a stipulated sum. AIA says to use A101-2017 when the full scope is defined at contract signing. Its contract sum article has places for alternates, allowances, unit prices and liquidated damages (Sections 4.2 to 4.5), and the bid form usually asks you to price the alternates and unit prices. Federal agencies must use sealed bids for construction in the United States when time allows, award will be on price and price-related factors, no discussions are needed and more than one bid is expected (FAR 36.103 and 6.401(a)).

The estimate is a detailed one: every item measured from the documents in a quantity takeoff and priced by trade, with subcontractor quotes compared scope for scope. It has to be complete on bid day, because the number is fixed and the documents define what it buys. What the drawings miss or contradict comes back after award as RFIs and change orders, so note the gaps while you price and ask before bids close.

04

CM at risk: estimating through design

AIA's A133-2019 splits the construction manager's work into a preconstruction phase and a construction phase. During preconstruction the CM prepares preliminary estimates "using area, volume, or similar conceptual estimating techniques," then updates the estimate of the cost of the work "with increasing detail and refinement" as the architect moves through schematic design, design development and construction documents (Section 3.1.6). Each estimate must allow for further design development, price escalation and market conditions, and the CM must tell the owner when it exceeds the approved budget and recommend corrective action. The CM does not warrant its estimates except as they become part of the GMP (Section 3.1.1).

At a time the owner and CM agree, the CM proposes a guaranteed maximum price: its estimate of the cost of the work, plus its contingency, plus its fee (Section 3.2.1). The GMP covers further development of the documents that is consistent with them and reasonably inferable from them. Changes in scope, systems, kinds and quality of materials, finishes or equipment come by change order (Section 3.2.2). The proposal lists the drawings and specifications it was priced from, the clarifications and assumptions, and the estimated cost by trade or system with allowances (Section 3.2.3). Our cost-plus guide covers how a GMP works once it is signed.

For trade contractors, a CM package is a bid to a builder with an extra reader. The CM obtains bids and delivers them to the owner and architect with the ones it intends to accept, and the owner may object to a bidder. If the owner insists on someone other than the CM's qualified, conforming recommendation, the CM can require a change order for the difference (A133 Sections 9.1 and 9.1.1). Expect the bid to be read line by line, because the owner pays actual cost.

05

Design-build: pricing a design that is not finished

The Design-Build Institute of America calls the single contract for design and construction the fundamental difference between design-build and the other methods. AIA's A141-2014 sets out the sequence. The owner states its criteria: program, design requirements, budget and milestone dates (Section 1.1). The design-builder evaluates them and reports with a preliminary estimate of the cost of the work and, if needed, recommendations to bring the criteria within the budget (Section 4.2.2). Next comes a preliminary design: site plan, plans, sections and elevations, structural system, major building systems including mechanical, electrical and plumbing, and outline specifications (Section 4.3.1).

Only then is the price proposed (Section 4.4.1). The proposal lists the documents it is based on, with the design-builder's clarifications, assumptions and deviations from the owner's criteria. It gives the contract sum and how it is paid, the substantial completion date, the qualifications and exclusions, and the date it expires. Once agreed, the design-builder produces the construction documents itself (Section 5.1.1). The price is fixed on a preliminary design, and developing it into construction documents is the design-builder's job and cost; a change to the owner's criteria needs a modification (Section 1.1.11).

Federal design-build uses two phases (FAR 36.3). In phase one, offerors submit their technical approach and qualifications, and price is not allowed. The contracting officer then asks the most highly qualified, normally no more than five, for phase-two proposals with separate technical and price parts (FAR 36.303-1 and 36.303-2). The contracting officer uses it when, among other tests, three or more offers are expected and offerors must do design work before they can price (FAR 36.301(b)).

DBIA names two common variations. In two-step best value design-build the owner shortlists the most qualified teams and then asks for design and cost proposals. In progressive design-build the design-builder is selected primarily on qualifications, and then the owner and design-builder advance the design and cost model together to an agreed design concept and contract price. Progressive design-build estimates through design like CM at risk, but with the design inside the builder's contract.

06

CM as adviser and integrated project delivery

With a construction manager as adviser, the CM is the owner's consultant and does not hold the trade contracts. AIA's set pairs C132-2019, between owner and CM, with A132-2019, which the owner signs with the contractor. In Canada, under CCDC 5A-2025 the CM acts as a limited agent of the owner and the trade contractors contract with the owner. CCDC 5B-2025 is the at-risk version: the CM also performs the work, at actual cost plus a fee, with options for a GMP or conversion to a stipulated price. Integrated project delivery under AIA C191-2009 puts owner, architect and contractor in one agreement with a target cost, and the parties share the savings when actual cost comes in below it (Section 1.1.2).

07

What the method means for your estimate

  • Know what the number becomes. A design-bid-build bid is a commitment on bid day. A CM preconstruction estimate is advice until the GMP. A design-build proposal becomes the contract sum when the owner accepts it.
  • Match the estimate to the design stage. Conceptual estimates price area or volume; detailed estimates price measured quantities. Our guide to types of construction estimates shows which fits each stage.
  • Write down the basis. GMP and design-build proposals both list the documents priced and the assumptions made (A133 3.2.3, A141 4.4.1). That list decides later whether a change is extra or included.
  • Price the time. Both proposals state the substantial completion date they assume, and the general conditions must cover the job to that date.
  • Keep contingency on its own line. In a GMP the CM's contingency covers costs not allocated to another line or a change order (A133 3.2.4); buried in trade prices, nobody can track it.
  • Track what moved between drawing issues. When the estimate is updated with each issue, a note of what changed the price saves the next argument about the budget.

08

Mistakes that cost money

  • Pricing a design-build proposal like a hard bid, from only what is drawn. Developing the design is the design-builder's cost, so price what the finished design will need, not only what the preliminary design shows.
  • Treating a CM preconstruction estimate as a quote. It changes with every issue and becomes a guarantee only in the GMP amendment.
  • Signing a GMP with a thin basis. If the drawing list, clarifications and assumptions are vague, every later scope question turns into an argument over money.
  • Absorbing changes as design development. Under A133 Section 3.2.2 a change in scope, systems or the kind and quality of materials is a change order; price it as one.
  • Leaving out escalation over a long preconstruction phase. A133 asks the CM's estimates to allow for price escalation and market conditions until the GMP is agreed.
  • Bidding a CM trade package without reading its scope. The CM draws the package lines, and they may not match the usual trade split.

09

A checklist before you price

  • The delivery method and the agreement form: A101, A133, A134, A141, CCDC 2, 5B, 14, or the owner's own.
  • What the number becomes: a bid, an estimate for review, a GMP proposal or a contract sum.
  • The drawing issue priced, listed sheet by sheet with dates.
  • Clarifications, assumptions, qualifications and exclusions written out.
  • Allowances and contingency on their own lines.
  • Escalation to the expected buyout dates.
  • The substantial completion date the price assumes.
  • For a trade bid: who you are bidding to (general contractor, CM or design-builder) and the package scope.
  • The date the proposal expires.

10

Where we fit

Whatever the method, a reliable price comes down to measured quantities priced by trade. For hard bids we prepare construction cost estimates and quantity takeoffs from the bid documents. For design-build and negotiated work we prepare early budget estimates and update them as the design develops, with notes on what changed the price between drawing issues: our design-build pricing support. We also price change orders from revised drawings. The estimating fee is $180–$250 per estimator per day, by project complexity; see how our fees work.

We estimate for general contractors and subcontractors across the United States and Canada. Send the drawings and we confirm the scope, fee and delivery date before work starts.

About the author

Navtej, Chief Estimator

B.Sc. in Civil Engineering, Master's in Quantity Surveying. Runs the estimating department, sets the standards every estimate is checked against and reviews high-stakes bids.

Meet the team

Questions contractors ask

What is the difference between design-build and design-bid-build?

In design-bid-build the owner signs two contracts in sequence: one with an architect for the design, then one with a contractor, usually chosen by bid on the finished documents. In design-build one contract covers both, so the design-builder prices the job on a preliminary design and is responsible for the design as well as the construction.

What is construction manager at risk?

A delivery method in which the owner hires the architect and a construction manager separately, and the CM joins during design. The CM gives estimates, schedules and constructability advice through design, then proposes a guaranteed maximum price and builds the job through subcontracts. AIA's agreement is A133-2019; Canada's is CCDC 5B-2025.

Is a CM at risk the same as a general contractor?

In construction the CM at risk holds the subcontracts and is responsible for the work, as a general contractor is. The differences are that it joins during design, is paid the cost of the work plus a fee, usually under a GMP, rather than a lump sum, and the owner sees the trade bids before they are accepted (A133 Section 9.1).

What is progressive design-build?

A design-build variation in which the owner selects the design-builder mainly on qualifications, then the two develop the design and the cost model together until they agree a design concept and a contract price. In two-step best value design-build, by contrast, teams submit design and cost proposals to win the job.

Which delivery method needs the most estimating?

CM at risk and progressive design-build, because the estimate is redone at each design stage before the price is fixed. Design-bid-build needs one complete detailed estimate at bid time. Design-build needs a full price on a preliminary design, so the estimate carries more allowances and qualifications.

Keep reading

Where this guide leads.

The services and sample estimates behind this guide, and the guides that pair with it.

Next bid

Bid due soon? Send the drawings.

Send the drawings, the scope and the bid date. We reply with a quote within 30 minutes during business hours.