Guide · Bidding

The Davis-Bacon Act: reading a wage determination and pricing labor from it.

The Davis-Bacon Act is the federal prevailing wage law for construction. On a job that carries it, the labor rates in the bid start from a wage determination in the bid documents, not from what the firm usually pays. Here is where the law applies, how to read a wage determination, how to price the base rate, fringes, overtime and apprentices from it, which revision governs a bid, and the mistakes that cost money.

  • Where Davis-Bacon applies, and who on the job it covers
  • How to read a wage determination, line by line
  • Pricing base rate, fringes, overtime and missing trades

Written by

Navtej, Chief Estimator

B.Sc. in Civil Engineering, Master's in Quantity Surveying. Runs the estimating department at E 4 Estimators.

  • 01

    Published November 24, 2026

  • 02

    10 min read

01

The short answer

The Davis-Bacon Act is the federal prevailing wage law for construction. Every federal contract over $2,000 for the construction, alteration or repair of a public building or public work, including painting and decorating, must state the minimum wages to be paid to the laborers and mechanics on it (40 U.S.C. 3142(a)). Those minimums are the wages the Secretary of Labor finds to be prevailing for each class of worker on similar projects in the area where the work is done (40 U.S.C. 3142(b)).

The minimums reach a bidder as a wage determination: a schedule bound into the solicitation that lists a basic hourly rate and a fringe benefit rate for each trade classification. For the estimator it sets the floor under every labor rate on that job. Read it wrong and the labor in the cost estimate is short from the first line.

02

Where it applies, and who it covers

On direct federal contracts the requirement arrives through FAR clause 52.222-6, Construction Wage Rate Requirements, which is the Federal Acquisition Regulation's name for the Davis-Bacon Act (FAR 22.403-1). It also reaches work that no federal agency signs. A group of funding laws known as the Related Acts carries the same labor standards onto construction they finance, in whole or in part, through federal grants, loans, guarantees or insurance (29 CFR 5.1 and 5.5(a)). So a state or city job with federal money in it can carry a Davis-Bacon wage determination.

The rates cover laborers and mechanics working on the site of the work. Under 29 CFR 5.2 that means workers whose duties are manual or physical, including apprentices and helpers. Administrative, executive and clerical staff are not covered. A working foreman who spends more than 20 percent of the week on trade work, and who is not an exempt manager, is covered for that time.

The site of the work is the place where the building will remain, any secondary site set up to build a significant portion of it, and yards, batch plants and similar facilities next to either that are dedicated to the project. A contractor's permanent shop or fabrication plant, whose location and operation do not depend on the project, is not part of the site. That matters when a trade splits its hours between shop and field: the split has to be right before the rates go on.

States are separate. Some have their own prevailing wage laws for state and local public work, with their own thresholds and rate schedules. California and New York do. Florida and Georgia have none, so on public work there prevailing wage arrives only with federal money. The bid documents say which schedule applies. If they do not, ask before bid day.

03

How to read a wage determination

General wage determinations are published on SAM.gov by state, county and type of construction (FAR 22.404-1). Where none fits, the agency asks the Department of Labor for a project wage determination, which is issued for one project and is good for 180 calendar days (29 CFR 1.6(a)(3)). Either way, the copy that counts is the one in the solicitation. A general determination reads like this:

General Decision Number and dateWhat it tells youWhich determination this isWhat to checkIt matches the number in the solicitation and its latest addendum
State and countiesWhat it tells youThe area the rates coverWhat to checkThe county where the work will be done is listed
Construction typeWhat it tells youBuilding, residential, highway or heavyWhat to checkIt is the type the solicitation assigns to your part of the work
Modification number and publication dateWhat it tells youEach revision since the determination was issuedWhat to checkYou are pricing from the revision that governs the bid
Identifier above each group of ratesWhat it tells youWhere the rate came from: a union agreement, a wage survey (SU), a union average (UAVG) or a state schedule (SA), with a dateWhat to checkUnion rates are updated as the agreements change; survey rates usually stay until a new survey
Rates and Fringes columnsWhat it tells youThe basic hourly rate and the hourly fringe benefit for each classificationWhat to checkBoth columns are owed for every hour worked
FootnotesWhat it tells youPaid holidays, vacation and other benefits that are not written as an hourly figureWhat to checkA cost that is easy to miss

The construction type decides which schedule you price from. The guidelines are in FAR 22.404-2(c). Building construction is sheltered enclosures with walk-in access that house people, machinery, equipment or supplies. Residential is single-family houses and apartment buildings of no more than four stories. Highway is roads, streets, runways, parking areas and similar work that is not incidental to another type. Heavy is everything else, such as dredging, water and sewer lines and dams. When a solicitation carries more than one schedule, the contracting officer has to state which work each one applies to. If that is unclear, ask before you price.

04

Pricing labor from the wage determination

Base rate plus fringe

The obligation is the total of the two columns. A contractor can meet it in cash wages, in contributions to bona fide fringe benefit plans, or in any mix of the two, as long as the total is not less than the basic hourly rate plus the fringe rate (40 U.S.C. 3142(d); 29 CFR 5.31). So carry both columns for every hour, whatever mix your firm uses. If your own benefit plans cost less per hour than the fringe column, the difference is paid in cash.

Benefits that the law already requires do not count toward the fringe (40 U.S.C. 3141(2)(B)). Payroll taxes and workers' compensation insurance stay in the labor burden, on top of the two columns.

Classification, apprentices and overtime

  • Workers are paid the rate for the classification of work actually performed, without regard to skill (29 CFR 5.5(a)(1)(i)). Build the crew from the classifications on the sheet, not from your own job titles.
  • A worker who does two kinds of work can be paid each rate for the hours spent in each, but only if the payroll records show the split accurately. If you cannot count on those records, price the higher rate.
  • Apprentices can be paid less than the listed rate only when they are individually registered in a program registered with the Department of Labor or a recognized state agency, and only within the program's ratio of apprentices to journeyworkers. Hours beyond the ratio are owed at the full rate (29 CFR 5.5(a)(4)).
  • Where the contract carries the overtime clause, FAR 52.222-4, hours over 40 in a week are paid at not less than one and one-half times the basic rate of pay. The premium is computed on the basic hourly rate, not on the fringe (29 CFR 5.32). The fringe is still owed, at its straight rate, for each overtime hour.

A trade that is not on the sheet

A missing classification does not mean any rate will do. After award, the contractor asks the contracting officer to add the classification and a proposed rate on Standard Form 1444 (FAR 22.406-3). It is approved only when the work is not performed by a classification already listed, the classification is used in the area by the construction industry, and the proposed rate bears a reasonable relationship to the rates on the determination (29 CFR 5.5(a)(1)(iii)). The rate that comes back is owed from the first day of work in that classification. Price a missing trade against comparable rates on the sheet, and say so in the bid's clarifications.

Subcontractors and paperwork

The clauses and the wage determination flow down to every tier, and the prime contractor is responsible for its subcontractors' compliance, including unpaid wages owed to the workers of lower-tier subcontractors (29 CFR 5.5(a)(6)). Check that each subcontractor's quote was priced from the determination. Every contractor and subcontractor also submits a certified payroll each week with a signed statement of compliance, on optional Form WH-347 or in another format, and keeps the records for at least three years after the work on the prime contract is completed (29 CFR 5.5(a)(3)). That office time belongs in the general conditions, not in the trade rates.

05

Which revision governs the bid

General wage determinations have no expiration date, and they are revised from time to time (29 CFR 1.6). Whether a revision applies to your bid depends on when it was published:

  • In sealed bidding, a revision published on SAM.gov 10 or more calendar days before bid opening is effective.
  • A revision published less than 10 calendar days before bid opening is also effective, unless the contracting officer finds there is not reasonable time left to notify bidders (FAR 22.404-6(b)).
  • In a negotiated procurement, a revision published before award is effective (FAR 22.404-6(c)).
  • In sealed bidding, a revision published after bid opening is not effective. The exception is an award that slips more than 90 days past bid opening: then a revision issued before award applies, unless the agency obtains an extension (29 CFR 1.6(c)(2)(ii)).
  • After award, the determination in the contract generally applies for the life of the contract. A newer one comes in when the contract is changed to add substantial work outside the original scope, or when an option to extend it is exercised (29 CFR 1.6(c)(2)(iii)).

In practice: note the modification number you priced from, read every addendum for a new one, and look at SAM.gov again inside the last two weeks before bid day. The determination is a minimum, not a forecast: if your labor agreement or the market pays more, price what you will pay.

06

Mistakes that cost money

  • Pricing the base rate and leaving out the fringe column.
  • Using the determination for the wrong county, or the residential schedule on a building job.
  • Pricing from the copy downloaded on day one and missing a modification that came with an addendum.
  • Carrying helpers or apprentices at reduced rates that the determination and the apprenticeship program do not allow.
  • Pricing by job title instead of by the work performed. A laborer who does carpentry is owed the carpenter's rate for those hours.
  • Accepting a subcontractor's quote that was priced at its usual rates.
  • Computing overtime on base plus fringe, or dropping the fringe from overtime hours.
  • Missing that a state or city job has federal money in it, and a Davis-Bacon determination with it.

07

A checklist before bid day

  • Which wage law applies: Davis-Bacon, a state law or both. If the documents are unclear, send a bid question in writing.
  • The determination number, modification number and date, taken from the solicitation and its latest addendum
  • The county and the construction type, and which schedule covers which part of the work
  • Each crew in the estimate matched to a classification on the sheet
  • Each rate built in order: base, fringe, the burden the law requires, then overhead and profit
  • The footnotes read for holidays, vacation and other benefits
  • Any missing classification listed, with the rate you assumed for it
  • Planned overtime priced on the basic rate, with the fringe carried on every hour
  • Subcontractors told the job is prevailing wage and sent the determination
  • Certified payroll time carried in the general conditions

08

Where we fit

We do not run payroll or advise on wage law. Our part is the estimate. Tell us when a bid is Davis-Bacon or state prevailing wage, and send the wage determination with the drawings: it changes the labor rates the estimate is built on. Our construction cost estimates are built from a quantity takeoff and organized by CSI division with quantities, units, material and labor on every line. The estimating fee is $180–$250 per estimator per day, by project complexity; see how our fees work. The sample estimates show the level of detail.

We estimate for general contractors and subcontractors across the United States and Canada. Send the drawings and we confirm the scope, fee and delivery date before work starts.

About the author

Navtej, Chief Estimator

B.Sc. in Civil Engineering, Master's in Quantity Surveying. Runs the estimating department, sets the standards every estimate is checked against and reviews high-stakes bids.

Meet the team

Questions contractors ask

What is the Davis-Bacon Act?

The federal prevailing wage law for construction. It requires every federal contract over $2,000 for the construction, alteration or repair of a public building or public work to state minimum wages for the laborers and mechanics on the job, based on the wages the Secretary of Labor finds prevailing in the area (40 U.S.C. 3142).

What is the difference between Davis-Bacon and prevailing wage?

Prevailing wage is the general term for a minimum wage set by law for public construction. Davis-Bacon is the federal law. With its Related Acts it covers federal construction and much federally assisted construction. Some states have their own prevailing wage laws for state and local projects, with their own rates and thresholds, and some have none.

What is a Davis-Bacon wage determination?

A schedule from the Department of Labor that lists the basic hourly rate and the fringe benefit rate for each trade classification, for one area and one type of construction. General wage determinations are published on SAM.gov, and the one that applies is included in the solicitation and the contract.

Are fringe benefits part of the Davis-Bacon wage?

Yes. The prevailing wage is the basic hourly rate plus the fringe rate. A contractor can pay the fringe into bona fide benefit plans, pay it to the worker in cash, or mix the two, as long as the total is not less than the two columns added together (40 U.S.C. 3142(d)).

Is overtime paid on fringe benefits under Davis-Bacon?

No. The overtime premium is computed on the basic hourly rate, and the fringe is left out of that calculation (29 CFR 5.32). The fringe itself is still owed at its straight rate for every hour worked, overtime hours included.

Keep reading

Where this guide leads.

The services and sample estimates behind this guide, and the guides that pair with it.